| Project | Jal Jeevan Mission- Kasaragod District- Kumbala Panchayath- RWSS to Kumbala Phase II-Part II- Laying Distribution and Providing FHTCs in Karle, Arikady Kadavath area |
|---|---|
| Project Code | KGDJJM08202927P2 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Kasaragod District- Kumbala Panchayath- RWSS to Kumbala Phase II |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission- Kasaragod District- Kumbala Panchayath- RWSS to Kumbala Phase II-Part II- Laying Distribution and Providing FHTCs in Karle, Arikady Kadavath area |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Kumbala PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 9990000 |
| TS Number | TS/2021-2022/2021/38345 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 16 Jul 2022 |
| Expected date of Completion | 31/08/2022 |
| TS Date | 09 Dec 2021 |
|---|---|
| Estimate Approval | 09 Dec 2021 |
| Tender Closing | 24 Dec 2021 |
| Price bid opening | 28 Dec 2021 |
| Workorder Date | 03 Jan 2022 |
|---|---|
| NA | 17 Jan 2022 |
| Kumbala PH Sn AE |
| Date: 13/09/2022 |
Work has been completed | 100% Completed
Work completed on 31/08/2022.
| Kumbala PH Sn AE |
| Date: 12/09/2022 |
Work in progress | 87% Completed
Work in progress.