- Home
- ARWSS to Kanjirappally, Elikkulam and Ch...
ARWSS to Kanjirappally, Elikkulam and Chirakkadavu Panchayath - State Plan 17-18 (Optimization)
Project |
ARWSS to Kanjirappally, Elikkulam and Chirakkadavu Panchayath - State Plan 17-18 (Optimization) |
Project Code |
KTMGOK1217705 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
SETC of 90 HP RW pumpset ,CW Pumpsets at Gramadeepam Boosting station and HT connection . |
Status |
Completed |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
8200000
|
AS Number |
G.O.(Rt.) No. 1040/2017/WRD dated 20/12/2017 |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
4983000 |
Total Bill Paid (Rs) |
4983000 |
Population Benefitted |
89758 |
Capacity in MLD |
9.00 |
Actual Project Completion Date |
15 Nov 2019 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
No Packages has been added for this project. |
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Nov 2021 |
3 Works were arranged in this. 1) 1No 90 HP VT pumpset at RWPH Karimpukayam. 2) CW pumpsets at CW booster PH Gramadeepam 3) Interconnection works at Gramdeepam PH . 1st one completed 0n 12/12/2018 , final bill submitted and the SD also relased as the DLP period also over . 2nd & 3rd completed and commissioned on 25/11/2019 after getting the HT connection at Gramadeepam CWBooster PH. Final bills were also submitted |
Kottayam Project Dn AE1 |
|
07 Nov 2021 |
2 Works were arranged in this. 1) 315kVA transformer, transformer building, CW pumpsets at WTP and Gramadeepam booster station, 2) 1No 90 HP VT pumpset at RWPH Karimpukayam. The second one completed 0n 12/12/2018 , final bill submitted and the SD also relased as the DLP period also over . 1st one completed and commissioned on 15/11/2019 after getting the HT connection at Gramadeepam CWBooster PH. The bill kept pending due to the non rectification of the deffects even after repeated reminders. Final bill submitted as per the direction from higher office to avoid the laps of NRDWP funds. Later the bill is resubmitted as per the directions as part bill for the approval of RE due to the Extra items arised and deviations done during the execution of Transformer Building. |
Kottayam Project Dn AE1 |
|
19 Aug 2020 |
completed |
Kottayam Project Dn AE1 |
|
Review Date |
Review Message |
Review Attended By |
27 Jan 2021 |
Completed project |
Exe Engineer |
Duration & Sanction dates
Date of start of Project |
27/06/2017 |
Scheduled date of Completion of the Project |
07 Nov 2017 |
Expected date of Completion |
30/11/2019 |