ARWSS to Kanjirappally, Elikkulam and Chirakkadavu Panchayath - State Plan 17-18 (Optimization)

Project ARWSS to Kanjirappally, Elikkulam and Chirakkadavu Panchayath - State Plan 17-18 (Optimization)
Project Code KTMGOK1217705
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description SETC of 90 HP RW pumpset ,CW Pumpsets at Gramadeepam Boosting station and HT connection .
Status Completed
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 8200000
AS Number G.O.(Rt.) No. 1040/2017/WRD dated 20/12/2017
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 4983000
Total Bill Paid (Rs) 4983000
Population Benefitted 89758
Capacity in MLD 9.00
Actual Project Completion Date 15 Nov 2019
Coverage

Packages

No. Project Name Location View
No Packages has been added for this project.

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Nov 2021 3 Works were arranged in this. 1) 1No 90 HP VT pumpset at RWPH Karimpukayam. 2) CW pumpsets at CW booster PH Gramadeepam 3) Interconnection works at Gramdeepam PH . 1st one completed 0n 12/12/2018 , final bill submitted and the SD also relased as the DLP period also over . 2nd & 3rd completed and commissioned on 25/11/2019 after getting the HT connection at Gramadeepam CWBooster PH. Final bills were also submitted Kottayam Project Dn AE1
07 Nov 2021 2 Works were arranged in this. 1) 315kVA transformer, transformer building, CW pumpsets at WTP and Gramadeepam booster station, 2) 1No 90 HP VT pumpset at RWPH Karimpukayam. The second one completed 0n 12/12/2018 , final bill submitted and the SD also relased as the DLP period also over . 1st one completed and commissioned on 15/11/2019 after getting the HT connection at Gramadeepam CWBooster PH. The bill kept pending due to the non rectification of the deffects even after repeated reminders. Final bill submitted as per the direction from higher office to avoid the laps of NRDWP funds. Later the bill is resubmitted as per the directions as part bill for the approval of RE due to the Extra items arised and deviations done during the execution of Transformer Building. Kottayam Project Dn AE1
19 Aug 2020 completed Kottayam Project Dn AE1

Project Review

See All Review messages
Review Date Review Message Review Attended By
27 Jan 2021 Completed project Exe Engineer

Duration & Sanction dates

Date of start of Project 27/06/2017
Scheduled date of Completion of the Project 07 Nov 2017
Expected date of Completion 30/11/2019

Processing Dates

AS Date 20 Dec 2017

Other details