Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2023-24 - WSS to Manathavady Edavaka and Nallornadu villages- Replacement of old AC pipes and line extension to various places in Mananthavady Municipality

Project State Plan 2023-24 - WSS to Manathavady Edavaka and Nallornadu villages- Replacement of old AC pipes and line extension to various places in Mananthavady Municipality
Project Code WYDGOK082314669
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description WSS to Manathavady Edavaka and Nallornadu villages- Replacement of old AC pipes and line extension to various places in Mananthavady Municipality.
Status On-going
District Wayanad
Executing Office Sulthan Bathery PH Dn
AS Amount (Rs) 10000000
AS Number KWA-JB/598/2023- AE 2
TS Amount (Rs) 10000000
TS Number WRD/KWA-CE(NR)/EST_TS/10348/2023_26_5_4
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 34000
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Replacement of old AC pipes and line extension to various places
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2023-24 - WSS to Manathavady Edavaka and Nallornadu villages- Replacement of old AC pipes and line extension to various places in Mananthavady Municipality Mananthavady PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 May 2024 Demand note issued from pwd Mananthavady PH Sn - AE
09 May 2024 Demand note issued from pwd Mananthavady PH Sn - AE
04 May 2024 Demand note issued from pwd Mananthavady PH Sn - AE
29 Apr 2024 awaiting for pwd permission Mananthavady PH Sn - AE
22 Apr 2024 pipe supplied and waiting for pwd permission Mananthavady PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/01/2024
Scheduled date of Completion of the Project 09 Sep 2024
Expected date of Completion 09/09/2024

Processing Dates

AS Date 05 Aug 2023
TS Date 10 Nov 2023

Other details

Project Officers View