AMRUT SAAP 2017-18 WSS to Palakkad Municipality Phase III Package II - Augmentation of Water Supply Scheme to Palakkad Municipality - Part III- Package II - Providing Rider main, changing of water connections and replacement of existing AC Pipelines to DI/PVC pipelines in Palakkad Muncipality
Project |
AMRUT SAAP 2017-18 WSS to Palakkad Municipality Phase III Package II - Augmentation of Water Supply Scheme to Palakkad Municipality - Part III- Package II - Providing Rider main, changing of water connections and replacement of existing AC Pipelines to DI/PVC pipelines in Palakkad Muncipality |
Project Code |
PKDAMRUT0518633 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Providing Rider main pipe lines, Replacing AC pipe lines and service connection for proper zoning |
Status |
Completed |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
851500000
|
AS Number |
GO(Rt) No.4165/LSGD |
TS Amount (Rs) |
543300000 |
TS Number |
KWA/CE/NR/43/2017-18 |
Total Bill Submitted (Rs) |
411524533 |
Total Bill Paid (Rs) |
398960027 |
Population Benefitted |
172683 |
Capacity in MLD |
42.00 |
Actual Project Completion Date |
30 May 2022 |
Coverage |
Palakkad Municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2017-18 Phase III-Package II PART III Palakkad WSS- Providing rider main pipe Replacement of AC pipe and water connection - Kalmandapam Zone |
Project Division Palakkad |
|
2 |
AMRUT 2017-18 Phase III-Package II PART II Palakkad WSS- Providing rider main pipe Replacement of AC pipe and water connection - Moothanthara Zone |
Project Division Palakkad |
|
3 |
AMRUT 2017-18 Phase III-Package II PART I Palakkad WSS- Providing rider main pipe Replacement of AC pipe and water connection - Mattumantha Zone |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 May 2022 |
All work completed |
Palakkad Proj AE 3 |
|
31 May 2022 |
All work completed |
Palakkad Proj AE 3 |
|
28 May 2022 |
Laying scope completed in all three zones Mattumantha Zone: 1812 old connections replaced, 512 new connections provided Moothanthara Zone: 1400 old connections replaced, 918 new connections provided Kalmandapam Zone: 1412 old connections replaced, 377 new connections provided |
Palakkad Project Dn AE 4 |
|
27 May 2022 |
Laying scope completed in all three zones Mattumantha Zone: 1812 old connections replaced, 512 new connections provided Moothanthara Zone: 1400 old connections replaced, 918 new connections provided Kalmandapam Zone: 1412 old connections replaced, 377 new connections provided |
Palakkad Project Dn AE 4 |
|
26 May 2022 |
Laying scope completed in all three zones Mattumantha Zone: 1812 old connections replaced, 512 new connections provided Moothanthara Zone: 1400 old connections replaced, 918 new connections provided Kalmandapam Zone: 1412 old connections replaced, 377 new connections provided |
Palakkad Project Dn AE 4 |
|
Review Date |
Review Message |
Review Attended By |
05 Nov 2021 |
Speed up the connection shifting work so as to commission the scheme by 30/11/2021 |
AEE,AE |
Duration & Sanction dates
Date of start of Project |
17/07/2018 |
Scheduled date of Completion of the Project |
25 Mar 2020 |
Expected date of Completion |
20/05/2022 |
Processing Dates
AS Date |
23 Dec 2017 |
TS Date |
23 Feb 2018 |