KDP Dist Pt 2020-21 RWSS to chittar Extension of pipe line from chittar old bus stand to jyothish nagar colony in chittar Pt (Old estimate no/2021/5123 revised with new SOR)
Project |
KDP Dist Pt 2020-21 RWSS to chittar Extension of pipe line from chittar old bus stand to jyothish nagar colony in chittar Pt (Old estimate no/2021/5123 revised with new SOR) |
Project Code |
PTADEPO052211653 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
KDP Dist Pt 2020-21 RWSS to chittar Extension of pipe line from chittar old bus stand to jyothish nagar colony in chittar Pt (Old estimate no/2021/5123 revised with new SOR) |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Ranni Sub Dn |
AS Amount (Rs) |
19163000
|
AS Number |
A2-2552/2021 |
TS Amount (Rs) |
1000000 |
TS Number |
TS/2022-2023/2022/8870 |
Total Bill Submitted (Rs) |
10 |
Total Bill Paid (Rs) |
10 |
Population Benefitted |
120 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
31 Oct 2022 |
Coverage |
Jjyothish Nagar colony in Chittar Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KDP Dist Pt 2020-21 RWSS to chittar Extension of pipe line from chittar old bus stand to jyothish nagar colony in chittar Pt (Old estimate no/2021/5123 revised with new SOR) |
Vadasserikara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Nov 2022 |
30% WORK IS COMPLEATED |
Vadasserikara PH Sn - AE |
|
17 Nov 2022 |
15% work is completed. |
Vadasserikara PH Sn - AE |
|
14 Nov 2022 |
work is started |
Vadasserikara PH Sn - AE |
|
08 Aug 2022 |
Agreement Executed on 01.08.2022 |
Pathanamthitta PH Dn EE |
|
16 Jul 2022 |
Selection Notice Issued |
Pathanamthitta PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/08/2022 |
Scheduled date of Completion of the Project |
31 Oct 2022 |
Expected date of Completion |
31/10/2022 |
Processing Dates
AS Date |
17 May 2022 |
TS Date |
08 Jun 2022 |