State Plan 2022-2023 - TWSS - Repacking of Filter Bed No.s 1 to 6 at 72 MLD WTP at Aruvikkara.

Project State Plan 2022-2023 - TWSS - Repacking of Filter Bed No.s 1 to 6 at 72 MLD WTP at Aruvikkara.
Project Code TVMGOK052211705
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2022-2023 - TWSS - Repacking of Filter Bed No.s 1 to 6 at 72 MLD WTP at Aruvikkara.
Status Completed
District Thiruvananthapuram
Executing Office Aruvikkara WS Gen Sn
AS Amount (Rs) 4000000
AS Number KWA/JB/PIU1/AE1/1/22
TS Amount (Rs) 4000000
TS Number 7590/2022-2023
Total Bill Submitted (Rs) 4186971
Total Bill Paid (Rs) 0
Population Benefitted 1500000
Capacity in MLD 48.00
Actual Project Completion Date 08 May 2023
Coverage Thiruvananthapuram City
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan - 2022 - 2023 - TWSS - Repacking of Filter Bed Nos. 1 to 6 at 72 MLD WTP at Aruvikkara. Aruvikkara WS Gen Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2023 Work completed satisfactorily Aruvikkara HW Gen Sn AE
05 May 2023 Filling filter sand in Bed No.3 Aruvikkara HW Gen Sn AE
02 May 2023 Filling filter media in Bed No.3 Aruvikkara HW Gen Sn AE
13 Apr 2023 Cleaning of Bed No. 1 at 48mld Aruvikkara HW Gen Sn AE
05 Apr 2023 Filling filter sand in Bed No.2 Aruvikkara HW Gen Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/07/2022
Scheduled date of Completion of the Project 14 Dec 2022
Expected date of Completion 14/12/2022

Processing Dates

AS Date 20 May 2022
TS Date 18 Jun 2022

Other details