AMRUT SAAP 2015-16 WSS to Palakkad Municipality Phase I - Providing new pumping main 600mm DI-K9 from Puthur Jn. to Moothanthara OHSR, Providing new pumping main 450mm DI-K9 from Mattumantha to Kalmandapam.

Project AMRUT SAAP 2015-16 WSS to Palakkad Municipality Phase I - Providing new pumping main 600mm DI-K9 from Puthur Jn. to Moothanthara OHSR, Providing new pumping main 450mm DI-K9 from Mattumantha to Kalmandapam.
Project Code PKDAMRUT0217595
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Replacement of CWPM to Moothanthara and Kalmandapam OHSRs with 600mm DI and 450mm DI Pipes
Status Completed
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 100000000
AS Number 534/2017/LSGD/TVM
TS Amount (Rs) 100000000
TS Number 544/AMRUT/TEC/NR/08/2017,456/AMRUT/TEC/NR/08/2017
Total Bill Submitted (Rs) 93338152
Total Bill Paid (Rs) 92581958
Population Benefitted 172683
Capacity in MLD 45.00
Actual Project Completion Date Date is not specified
Coverage Part of Palakkad muncipality with total capacity of 45mld
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT SAAP 2015-16 Phase 1 Part 1 - 600mm DI K9 CWPM from Puthur to Moothanthara OHSR Project Division Palakkad
2 AMRUT SAAP 2015-16 Phase 1 Part 2 - 450mm DI K9 CWPM from Mattumantha to Kalmandapam OHSR Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Nov 2020 Works completed Palakkad Project Dn AE 4
29 Sep 2020 600mm DI K9 : laying works completed, linking work to new OHSR remaining. 450mm DI K9: Trial run in progress Palakkad Project Dn AE 4
14 Sep 2020 600mm DI K9 : laying works completed, linking work to new OHSR remaining. 450mm DI K9: Trial run in progress Palakkad Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/01/2018
Scheduled date of Completion of the Project 03 Jan 2019
Expected date of Completion 30/11/2020

Processing Dates

AS Date 23 Feb 2017
TS Date 05 Jun 2017

Other details