Amrut -2015-16-WSS to Thrissur corporation-Survey and Replacing of Faulty water meters and fixing new water meters at various service connections in Thrissur Corporation area.

Project Amrut -2015-16-WSS to Thrissur corporation-Survey and Replacing of Faulty water meters and fixing new water meters at various service connections in Thrissur Corporation area.
Project Code TCRAMRUT03161071
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description 1Supply & installation of( 754 nos) meter 2 . Supply & laying 7120m pipe 3 Providing New service connection(500 nos)
Status Completed
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 30000000
AS Number GO(Rt) No.1329/2016/LSGD
TS Amount (Rs) 30000000
TS Number CE/CR/KWA/4/2016-17
Total Bill Submitted (Rs) 13260000
Total Bill Paid (Rs) 13260000
Population Benefitted 8500
Capacity in MLD 20.00
Actual Project Completion Date 20 Dec 2021
Coverage Thrissur corporation
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Amrut -2015-16-WSS to Thrissur corporation-Survey and Replacing of Faulty water meters and fixing new water meters at various service connections in Thrissur Corporation area. Thrissur WW Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Jan 2023 Final Bill paid on 17/06/2022 Thrissur PH Dn EE
07 Nov 2021 Work Completed Thrissur PH Dn EE
13 Sep 2021 500/500 NOS CONNECTION GIVEN,PIPE LAYING WORK COMPLETED,484/750 NOS FAULTY METER REPLACED. The core committee on 22.7.2021 has decided to provide the list of damaged meter in the old municipal area as soon as possible. But the list is not received till date. The work can be completed with a week after receiving the list. Thrissur PH Dn EE
28 Aug 2021 500/500 NOS CONNECTION GIVEN,PIPE LAYING WORK COMPLETED,484/750 NOS FAULTY METER REPLACED. The core committee on 22.7.2021 has decided to provide the list of damaged meter in the old municipal area as soon as possible. But the list is not received till date. The work can be completed with a week after receiving the list. Thrissur PH Dn EE
28 Aug 2021 498/500 NOS CONNECTION GIVEN,PIPE LAYING WORK COMPLETED,484/750 NOS FAULTY METER REPLACED. The core committee on 22.7.2021 has decided to provide the list of damaged meter in the old municipal area as soon as possible. But the list is not received till date. The work can be completed with a week after receiving the list. Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/12/2017
Scheduled date of Completion of the Project 18 Jun 2018
Expected date of Completion 31/10/2021

Processing Dates

AS Date 26 Mar 2016
TS Date 18 Apr 2016

Other details