Amrut -2015-16-WSS to Thrissur corporation-Survey and Replacing of Faulty water meters and fixing new water meters at various service connections in Thrissur Corporation area.
Project |
Amrut -2015-16-WSS to Thrissur corporation-Survey and Replacing of Faulty water meters and fixing new water meters at various service connections in Thrissur Corporation area. |
Project Code |
TCRAMRUT03161071 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
1Supply & installation of( 754 nos) meter 2 . Supply & laying 7120m pipe 3 Providing New service connection(500 nos) |
Status |
Completed |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
30000000
|
AS Number |
GO(Rt) No.1329/2016/LSGD |
TS Amount (Rs) |
30000000 |
TS Number |
CE/CR/KWA/4/2016-17 |
Total Bill Submitted (Rs) |
13260000 |
Total Bill Paid (Rs) |
13260000 |
Population Benefitted |
8500 |
Capacity in MLD |
20.00 |
Actual Project Completion Date |
20 Dec 2021 |
Coverage |
Thrissur corporation |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Amrut -2015-16-WSS to Thrissur corporation-Survey and Replacing of Faulty water meters and fixing new water meters at various service connections in Thrissur Corporation area. |
Thrissur WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Jan 2023 |
Final Bill paid on 17/06/2022
|
Thrissur PH Dn EE |
|
07 Nov 2021 |
Work Completed |
Thrissur PH Dn EE |
|
13 Sep 2021 |
500/500 NOS CONNECTION GIVEN,PIPE LAYING WORK COMPLETED,484/750 NOS FAULTY METER REPLACED. The core committee on 22.7.2021 has decided to provide the list of damaged meter in the old municipal area as soon as possible. But the list is not received till date. The work can be completed with a week after receiving the list. |
Thrissur PH Dn EE |
|
28 Aug 2021 |
500/500 NOS CONNECTION GIVEN,PIPE LAYING WORK COMPLETED,484/750 NOS FAULTY METER REPLACED. The core committee on 22.7.2021 has decided to provide the list of damaged meter in the old municipal area as soon as possible. But the list is not received till date. The work can be completed with a week after receiving the list. |
Thrissur PH Dn EE |
|
28 Aug 2021 |
498/500 NOS CONNECTION GIVEN,PIPE LAYING WORK COMPLETED,484/750 NOS FAULTY METER REPLACED. The core committee on 22.7.2021 has decided to provide the list of damaged meter in the old municipal area as soon as possible. But the list is not received till date. The work can be completed with a week after receiving the list. |
Thrissur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/12/2017 |
Scheduled date of Completion of the Project |
18 Jun 2018 |
Expected date of Completion |
31/10/2021 |
Processing Dates
AS Date |
26 Mar 2016 |
TS Date |
18 Apr 2016 |