AMRUT - Kannur Corporation - Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Puzhathi zone

Project AMRUT - Kannur Corporation - Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Puzhathi zone
Project Code KNRAMRUT09173127
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Rehabilitation of existing distribution network, valves, house service connection and interconnection with existing lines of Puzhathi zone of Kannur Corporation.Total distribution line -39755m(600mm DI pipe225m,500mm DI pipe-1605m,400mm DI pipe-1780m,350mm DI pipe-500m.300mm DI pipe-300m,250mm DI pipe-5290m,200mm DI pipe-3440m and 160mm PVC-26615m).
Status Completed
District Kannur
Executing Office Kannur Project Dn
AS Amount (Rs) 177000000
AS Number
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 132128522
Total Bill Paid (Rs) 171628522
Population Benefitted 35212
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage 35212(Population) 7083(Habitation)

Packages

No. Project Name Location View
1 AMRUT - Kannur Corporation - Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Puzhathi zone - Package - I Kannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jan 2021 100% work completed Koothuparamba Project Sn No 1
05 Jan 2021 New house connections completed. Koothuparamba Project Sn No 1
16 Nov 2020 98% completed Koothuparamba Project Sn No 1
12 Sep 2020 95% distribution network completed and charged. Shifting of existing house connection and interconnection works are progressing. New house connection work pending . Koothuparamba Project Sn No 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/03/2018
Scheduled date of Completion of the Project 06 Mar 2019
Expected date of Completion 31/12/2020

Processing Dates

AS Date 28 Sep 2017
TS Date 10 Nov 2017
Estimate Approval 10 Nov 2017
Tender Closing 26 Dec 2017
Technichal Pre-Qualification 09 Jan 2018
Price bid opening 10 Jan 2018

Approval Dates

Head Office Approval 03 Mar 2018
Workorder Date 07 Mar 2018
NA 20 Mar 2018

Other details

Project Officers View