Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

REBUILD-AUWSS to Panniyanoor town and Panoor Mokeri villages - Automation (II)-Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 1 No -30 Hp Vertical Turbine pump sets at Raw water Pump house at pathipalam-General Electrical Work

Project REBUILD-AUWSS to Panniyanoor town and Panoor Mokeri villages - Automation (II)-Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 1 No -30 Hp Vertical Turbine pump sets at Raw water Pump house at pathipalam-General Electrical Work
Project Code KNRRKI042216739
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description REBUILD-AUWSS to Panniyanoor town and Panoor Mokeri villages - Automation (II)-Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 1 No -30 Hp Vertical Turbine pump sets at Raw water Pump house at pathipalam-General Electrical Work
Status Completed
District Kannur
Executing Office Thalassery PH Sn
AS Amount (Rs) 1650000
AS Number 6296/AE1 (OPERATIONS)/2022/KWA
TS Amount (Rs) 150000
TS Number 12598/2024-2025
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 31 Dec 2024
Coverage

Packages

No. Project Name Location View
1 REBUILD-AUWSS to Panniyanoor town and Panoor Mokeri villages - Automation (II)-Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 1 No -30 Hp Vertical Turbine pump sets at Raw water Pump house at pathipalam-General Electrical Work Thalassery PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Dec 2024 Work completed Thalassery PH Sn AE
25 Oct 2024 Agreement executed. Thalassery PH Sn AE
21 Oct 2024 Agreement executed Kannur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 19 Apr 2022
TS Date 05 Sep 2024

Other details

Project Officers View