Project | Deposit-Payyannur Municipality2023-24 plan-Pipeline extension to various places-pipeline work |
---|---|
Project Code | KNRDEPO042416554P1 |
Type | Package |
Main Project | Deposit-Payyannur Municipality2023-24 plan-Pipeline extension to various places-pipeline work |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit-Payyannur Municipality2023-24 plan-Pipeline extension to various places-pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Payyannur WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 3750000 |
TS Number | 11470/2024-25 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 23 Aug 2024 |
---|---|
Estimate Approval | 23 Aug 2024 |
NIT Approval | 23 Aug 2024 |
Tender Closing | 30 Aug 2024 |
Technichal Pre-Qualification | 30 Aug 2024 |
Workorder Date | 13 Sep 2024 |
---|
Thaliparamba WS Dn EE |
Date: 01/07/2025 |
Work in progress | 92% Completed
75mm pvc pipe-1000m,90mm pvc pipe- 2500m completed .
Thaliparamba WS Dn EE |
Date: 26/06/2025 |
Work in progress | 92% Completed
75mm pvc pipe-1000m,90mm pvc pipe- 2500m completed.