| Project | FHTC in Vazhayur |
|---|---|
| Project Code | MLPJJM08202868P1 |
| Type | Package |
| Main Project | JJM WSS to Cheekode and Adjoining Villages- Providing FHTC toVazhayur Panchayath. |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Providing 5740FHTC in Vazhayur GP with extension distribution line after conducting detailed survey & design |
| Status | On-going |
| District | Malappuram |
| Executing Office | Malappuram Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 162200000 |
| TS Number | TS/2020/20658 dated 17/09/2020 |
| Technical specification | Providing 5740FHTC in Vazhayur GP with extension distribution line after conducting detailed survey & design |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/01/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 16 Dec 2021 |
| Expected date of Completion | 31/03/2023 |
| TS Date | 17 Sep 2020 |
|---|
| Workorder Date | 03 Nov 2020 |
|---|---|
| NA | 17 Dec 2020 |
| Malapuram Proj Dn AE 4 |
| Date: 15/06/2023 |
Work has been completed | 100% Completed
Work completed on 31/01/2023.
| Malapuram Proj Dn AE 4 |
| Date: 14/06/2023 |
Work in progress | 77% Completed
4750 Nos of FHTCs has been provided and work has been due to shortage of GI pipe. There was a huge protest from public against trenching and demanded for GI pipe. Even after several meetings, it had been decided to short close the work and rearrange.