Project Code ALPDEPO03197474
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work: Jilla panchayath :Nooranadu Division - RWSS to Nooranad - WSS to Clathara Colony - Pipe line extension at various places in Cherumugha (ward No:2) of Nooranad Grama Pancayath.
Status Completed
District Alappuzha
Executing Office Mavelikkara WS Sn
AS Amount (Rs) 1190000
AS Number A
TS Amount (Rs) 1190000
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 860
Capacity in MLD 0.70
Actual Project Completion Date 28 Mar 2020
Coverage

Packages

No. Project Name Location View
1 Deposit work: Jilla panchayath :Nooranadu Division - RWSS to Nooranad - WSS to Clathara Colony - Pipe line extension at various places in Cherumugha (ward No:2) of Nooranad Grama Pancayath. Mavelikkara WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jul 2021 Work Completed,Final Bill Submitted Alappuzha PH Dn EE
05 Jul 2021 Work Completed,Final Bill Submitted Alappuzha PH Dn EE
28 Jun 2021 Work Completed,Final Bill Submitted Alappuzha PH Dn EE
11 Jun 2021 Work Completed,Final Bill Submitted Alappuzha PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/10/2018
Scheduled date of Completion of the Project 14 Mar 2020
Expected date of Completion 21/07/2021

Processing Dates

AS Date 11 Mar 2019
TS Date 11 Mar 2019

Other details