Project | DRW 2022- CWSS to Chithara and adjoining Panchayaths |
---|---|
Project Code | KLMGOK032210140 |
Type | Main project |
Funding Agency | GOK |
Category | DRW |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | DRW 2022- CWSS to Chithara and adjoining Panchayaths - Mylamoode Pump House - Repair of 150 HP slow speed heavy body type vertical turbine pump set , making/supplying specials for the work |
Status | Completed |
District | Kollam |
Executing Office | Kadakkal PH Sub Dn |
AS Amount (Rs) | 500000 |
AS Number | 3476/AEII(OP)/2020/KWA(III) |
TS Amount (Rs) | 187202 |
TS Number | TS/2022-2023/2022/11489 |
Total Bill Submitted (Rs) | 0 |
Total Bill Paid (Rs) | 0 |
Population Benefitted | 9000 |
Capacity in MLD | 9.70 |
Actual Project Completion Date | Date is not specified |
Coverage | full coverage |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 May 2022 | 100% completed | Madathara PH Sn - AE | |
27 May 2022 | Work is in progress | Kottarakkara PH Dn EE | |
26 May 2022 | 70% completed, works going on | Madathara PH Sn - AE | |
23 May 2022 | 65% completed, works going on | Madathara PH Sn - AE | |
19 May 2022 | 60% completed, works going on | Madathara PH Sn - AE |
Date of start of Project | 21/04/2022 |
---|---|
Scheduled date of Completion of the Project | 06 May 2022 |
Expected date of Completion | 31/05/2022 |
AS Date | 30 Mar 2022 |
---|---|
TS Date | 11 Apr 2022 |
Project Officers | View |
---|