Amrut 2.0 (2022-23)-Augmentation of Water supply scheme in Sulthan Bathery Municipality and providing FHTCs .
Project |
Amrut 2.0 (2022-23)-Augmentation of Water supply scheme in Sulthan Bathery Municipality and providing FHTCs . |
Project Code |
WYDAMRUT 2022313826 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Augmentation of Water supply scheme in Sulthan Bathery Municipality and providing FHTCs . |
Status |
On-going |
District |
Wayanad |
Executing Office |
Sulthan Bathery PH Dn |
AS Amount (Rs) |
136270000
|
AS Number |
G.O.(Rt)No.473/2023/LSGD |
TS Amount (Rs) |
130900000 |
TS Number |
TS/1584/2022_26_1_1 |
Total Bill Submitted (Rs) |
97322439 |
Total Bill Paid (Rs) |
97322439 |
Population Benefitted |
500 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
nil |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Amrut 2.0(2022-23)-Augmentation of Water supply scheme in Sulthan Bathery Municipality and providing FHTCs . |
Sulthan Bathery Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Pipe laying works are completed. Inter connection works along with balance base concrete works including Road restoration and geo tagging are in progress. |
Sulthan Bathery PH Sn - AE |
|
08 May 2024 |
Pipe laying works are completed. Inter connection works along with balance base concrete works including Road restoration and geo tagging are in progress. |
Sulthan Bathery PH Sn - AE |
|
04 May 2024 |
Pipe laying works are completed. Inter connection works along with balance base concrete works including Road restoration and geo tagging are in progress. |
Sulthan Bathery PH Dn EE |
|
30 Apr 2024 |
Pipe laying works are completed. Inter connection works along with balance House connection crossing and base concrete works including Road restoration and geo tagging are in progress. |
Sulthan Bathery PH Sn - AE |
|
25 Apr 2024 |
Pipe laying works are completed. Inter connection works along with balance House connection crossing and base concrete works including Road restoration and geo tagging are in progress. |
Sulthan Bathery PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/02/2023 |
Scheduled date of Completion of the Project |
29 Jun 2024 |
Expected date of Completion |
29/06/2024 |
Processing Dates
AS Date |
02 Feb 2023 |
TS Date |
26 Apr 2023 |