State Plan--2022-23- RWSS to Vettoor- Supply and errection of 20 HP Submersible pumpset at Vilabhagom Pump House - under section No.2, Varkala -
Project |
State Plan--2022-23- RWSS to Vettoor- Supply and errection of 20 HP Submersible pumpset at Vilabhagom Pump House - under section No.2, Varkala - |
Project Code |
TVMGOK052213394 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan--2022-23- RWSS to Vettoor- Supply and errection of 20 HP Submersible pumpset at Vilabhagom Pump House - under section No.2, Varkala - |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Varkala WS Sn 2 |
AS Amount (Rs) |
488000
|
AS Number |
KWA/JB/PIU 1/AE1/5/2022 |
TS Amount (Rs) |
476790 |
TS Number |
ORDER No. 5485/2022-2023 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan--2022-23- RWSS to Vettoor- Supply and errection of 20 HP Submersible pumpset at Vilabhagom Pump House - under section No.2, Varkala - |
Varkala WS Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Mar 2023 |
Pump erected on 13th march 2023 |
Varkala WS Sn - 2 AE |
|
13 Mar 2023 |
pumpset inspected on 2 nd march |
Varkala WS Sn - 2 AE |
|
09 Mar 2023 |
pumpset inspected on 2 nd march |
Varkala WS Sn - 2 AE |
|
06 Mar 2023 |
pumpset inspected on 2 nd march |
Varkala WS Sn - 2 AE |
|
03 Mar 2023 |
pumpset inspected on 2 nd march |
Varkala WS Sn - 2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/01/2023 |
Scheduled date of Completion of the Project |
15 Jun 2023 |
Expected date of Completion |
15/06/2023 |
Processing Dates
AS Date |
24 May 2022 |
TS Date |
14 Nov 2022 |