- Home
- STATE PLAN2023-24 PROVIDING LEVEL INDICA...
STATE PLAN2023-24 PROVIDING LEVEL INDICATORS,CCTV AND COMPOUND WALL AT MR HILL PUMP HOUSE UNDER WW SECTION, KURIATHY.
Project |
STATE PLAN2023-24 PROVIDING LEVEL INDICATORS,CCTV AND COMPOUND WALL AT MR HILL PUMP HOUSE UNDER WW SECTION, KURIATHY. |
Project Code |
TVMGOK092215374 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
STATE PLAN2023-24 PROVIDING LEVEL INDICATORS,CCTV AND COMPOUND WALL AT MR HILL PUMP HOUSE UNDER WW SECTION, KURIATHY. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Kuriyathi South Sub Dn |
AS Amount (Rs) |
5
|
AS Number |
PIUI/SP/45/2023_24 |
TS Amount (Rs) |
5 |
TS Number |
|
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
STATE PLAN2023-24 PROVIDING LEVEL INDICATORS,CCTV AND COMPOUND WALL AT MR HILL PUMP HOUSE UNDER WW SECTION, KURIATHY. |
Kuriathy Sn(Maintenance) |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/12/2023 |
Scheduled date of Completion of the Project |
01 Mar 2024 |
Expected date of Completion |
01/03/2024 |
Processing Dates
AS Date |
02 Sep 2023 |
TS Date |
13 Sep 2023 |