State Plan 2021-22 TSS - D Block - Zone II - Supplying Conveying and Laying 700mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam to Kannamoola - Ch 0 to 342m
Project |
State Plan 2021-22 TSS - D Block - Zone II - Supplying Conveying and Laying 700mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam to Kannamoola - Ch 0 to 342m |
Project Code |
TVMGOK05217477 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan 2021-22 TSS - D Block - Zone II - Supplying Conveying and Laying 700mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam to Kannamoola - Ch 0 to 342m |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Plamoodu project Sn |
AS Amount (Rs) |
14600000
|
AS Number |
KWA/JB/PIU1/AE1/12/2021 |
TS Amount (Rs) |
14600000 |
TS Number |
18413/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100000 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
07 Sep 2022 |
Coverage |
State Plan 2021-22 TSS - D Block - Zone II - Supplying Conveying and Laying 700mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam to Kannamoola - Ch 0 to 342m |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2021-22 TSS - D Block - Zone II - Supplying Conveying and Laying 700mm dia RCC NP3 pipe sewer trunk main II from Murinjapalam to Kannamoola - Ch 0 to 342m |
Plamoodu project Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
04 May 2024 |
Earth filling work inside the cement bag for the construction of temporary bund across the thodu is going on. |
Plamoodu Sewerage Project Sn AE |
|
02 May 2024 |
Earth filling work inside the cement bag for the construction of temporary bund across the thodu is going on. |
Plamoodu Sewerage Project Sn AE |
|
20 Apr 2024 |
Contractor was given a reminder letter directing to complete the work immediately |
Plamoodu Sewerage Project Sn AE |
|
10 Apr 2024 |
Contractor was given a reminder letter directing to complete the work immediately |
Plamoodu Sewerage Project Sn AE |
|
31 Mar 2024 |
Non objection certificate for thodu crossing received from the Irrigation Department. Contractor was given a reminder letter directing to complete the work immediately. |
Plamoodu Sewerage Project Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/03/2022 |
Scheduled date of Completion of the Project |
07 Sep 2022 |
Expected date of Completion |
24/07/2023 |
Processing Dates
AS Date |
28 Dec 2021 |
TS Date |
21 Jan 2022 |