Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 31 Nos Vertical Turbine pump sets in 225 MLD WTP at Aluva

Project Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 31 Nos Vertical Turbine pump sets in 225 MLD WTP at Aluva
Project Code EKMRKI042211850P1
Type Package
Main Project Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 31 Nos Vertical Turbine pump sets in 225 MLD WTP at Aluva
Status On-going
District Ernakulam
Executing Office Aluva HW Sn
Agreement Number
Agreement Date
TS Amount (Rs) 4650000
TS Number TS/2022-2023/2022/23337 Dated: 03-07-2022
Technical specification TS/2022-2023/2022/23337 Dated: 03-07-2022
Contractor VOLLWERT ELECTRIC PRIVATE LIMITED (Mob: 9567863491)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/08/2022
Scheduled date of Completion as per agreement 15 Sep 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 03 Jul 2022
Estimate Approval 03 Jul 2022
NIT Approval 03 Jul 2022
Tender Closing 03 Jul 2022
Technichal Pre-Qualification 03 Jul 2022
Price bid opening 03 Jul 2022

Approval Dates

Workorder Date 02 Aug 2022
NA 30 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Aluva AE HW
Date: 17/05/2024

Work in progress | 99% Completed

Automation works in progress.

Aluva AE HW
Date: 16/05/2024

Work in progress | 99% Completed

Automation works in progress.