AMRUT 2.0-Improving Production Capacity of 100MLD WTP- Supply and fixing of VT pump sets at RWPH, Pazhoor-Improving Production Capacity of 100MLD WTP, Maradu- Supply and fixing of VT pump sets at RWPH, Pazhoor-General Civil Work
Project |
AMRUT 2.0-Improving Production Capacity of 100MLD WTP- Supply and fixing of VT pump sets at RWPH, Pazhoor-Improving Production Capacity of 100MLD WTP, Maradu- Supply and fixing of VT pump sets at RWPH, Pazhoor-General Civil Work |
Project Code |
EKMAMRUT112214183P1 |
Type |
Package |
Main Project |
AMRUT 2.0 -Improving Production Capacity of 100MLD WTP- Supply and fixing of VT pump sets at RWPH, Pazhoor-Improving Production Capacity of 100MLD WTP, Maradu- Supply and fixing of VT pump sets at RWPH, Pazhoor-General Civil Work
|
Funding Agency |
AMRUT |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2.0-Improving Production Capacity of
100MLD WTP- Supply and fixing of VT pump
sets at RWPH, Pazhoor-Improving Production
Capacity of 100MLD WTP, Maradu- Supply
and fixing of VT pump sets
at RWPH, Pazhoor-General Civil Work |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Vytilla Head works |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
43200000 |
TS Number |
14092/2022-23 |
Technical specification |
Improving Production Capacity of
100MLD WTP- Supply and fixing of VT pump
sets at RWPH, Pazhoor-Improving Production |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
18/05/2023 |
Scheduled date of Completion as per agreement |
05 Nov 2023 |
Expected date of Completion |
05/11/2023 |
Processing Dates
TS Date |
15 Feb 2023 |
Estimate Approval |
28 Feb 2023 |
NIT Approval |
01 Mar 2023 |
Tender Closing |
09 Mar 2023 |
Technichal Pre-Qualification |
10 Mar 2023 |
Price bid opening |
10 Mar 2023 |
Approval Dates
Workorder Date |
06 May 2023 |
NA |
18 May 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Vytilla HW AE |
Date: 04/05/2024 |
Work in progress | 88% Completed
work in progress.
Vytilla HW AE |
Date: 06/04/2024 |
Work in progress | 86% Completed
work in progress.