GIDA - Water Supply Scheme to Elamkunnapuzha, Njarakkal and Nayarambalam Panchayaths
Project |
GIDA - Water Supply Scheme to Elamkunnapuzha, Njarakkal and Nayarambalam Panchayaths |
Project Code |
EKMGOK06115971 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Balance work - Construction of 11.80 lakhs litres OHS Reservoir at Murikkumpadam & Construction of 17.90 lakhs litres OHS Reservoir at Njarackal in Zone III |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
568500000
|
AS Number |
G.O.( MS) No.115/2011/LSGD/TVM |
TS Amount (Rs) |
21200000 |
TS Number |
TS/2020-2021/2531 |
Total Bill Submitted (Rs) |
58362037 |
Total Bill Paid (Rs) |
58362037 |
Population Benefitted |
138276 |
Capacity in MLD |
26.00 |
Actual Project Completion Date |
10 Feb 2022 |
Coverage |
Elamkunnapuzha, Njarakkal and Nayarambalam Panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Balance work - Construction of 11.80 lakhs litres OHS Reservoir at Murikkumpadam |
Project Division Perumbavoor |
|
2 |
Construction of 17.90 lakhs litres OHS Reservoir at Njarackal |
Project Division Perumbavoor |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Mar 2023 |
work completed |
Perumbavoor Project Dn AE1 |
|
15 Mar 2023 |
For njarackal Floor concreting completed and water to be filled for testing. |
Perumbavoor Project Dn AE1 |
|
14 Mar 2023 |
For njarackal Floor concreting completed and water to be filled for testing. |
Perumbavoor Project Dn AE1 |
|
13 Mar 2023 |
For njarackal Floor concreting completed and water to be filled for testing. |
Perumbavoor Project Dn AE1 |
|
12 Mar 2023 |
For njarackal Floor concreting completed and water to be filled for testing. |
Perumbavoor Project Dn AE1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/02/2021 |
Scheduled date of Completion of the Project |
19 Aug 2021 |
Expected date of Completion |
21/04/2022 |
Processing Dates
AS Date |
22 Jun 2011 |
TS Date |
02 Feb 2021 |