Deposit work -ARWSS - to Krishnagiri ,Purakkadi and Ambalavayal Villages -Extension of pipe line in Ward no. 10 in Meenangadi Grama Panchayath

Project Deposit work -ARWSS - to Krishnagiri ,Purakkadi and Ambalavayal Villages -Extension of pipe line in Ward no. 10 in Meenangadi Grama Panchayath
Project Code WYDDEPO03217882
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work -ARWSS - to Krishnagiri ,Purakkadi and Ambalavayal Villages -Extension of pipe line in Ward no. 10 in Meenangadi Grama Panchayath
Status Completed
District Wayanad
Executing Office Sulthan Bathery Sn
AS Amount (Rs) 459000
AS Number AS NO. A2-2659/21
TS Amount (Rs) 459000
TS Number TS/2021-2022/2021/1059
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Krishnagiri ,Purakkadi and Ambalavayal Villages
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work -ARWSS - to Krishnagiri ,Purakkadi and Ambalavayal Villages -Extension of pipe line in Ward no. 10 in Meenangadi Grama Panchayath Sulthan Bathery Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Nov 2021 Work completed Sulthan Bathery PH Dn EE
09 Nov 2021 Work Under Progress Sulthan Bathery PH Dn EE
06 Nov 2021 Work in Progress Sulthan Bathery PH Dn EE
29 Oct 2021 Work in progress Sulthan Bathery PH Dn EE
25 Oct 2021 Work in progress Sulthan Bathery PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/07/2021
Scheduled date of Completion of the Project 28 Jan 2022
Expected date of Completion 28/01/2022

Processing Dates

AS Date 23 Mar 2021
TS Date 26 May 2021

Other details