Jal jeevan Mission Phase 1 - Providing FHTC , Pipe line Extension and Replacement of Existing AC distribution main in Elampalloor Grama Panchayath
Project |
Jal jeevan Mission Phase 1 - Providing FHTC , Pipe line Extension and Replacement of Existing AC distribution main in Elampalloor Grama Panchayath |
Project Code |
KLMJJM08203183 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing FHTC , Pipe line Extension and Replacement of Existing AC distribution main |
Status |
On-going |
District |
Kollam |
Executing Office |
Kottarakkara PH Sn |
AS Amount (Rs) |
200370000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
157000000 |
TS Number |
6730/2020-2021 |
Total Bill Submitted (Rs) |
82723707 |
Total Bill Paid (Rs) |
82039033 |
Population Benefitted |
31112 |
Capacity in MLD |
3.00 |
Actual Project Completion Date |
31 Aug 2024 |
Coverage |
7778 Families |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Jal jeevan Mission Phase 1 - Providing FHTC , Pipe line Extension and Replacement of Existing AC distribution main in Elampalloor Grama Panchayath - Balance Work.-Laying of 63 mm, 75 mm PVC Pipes and 50 mm, 65 mm, and 80 mm G.I. Pipes in balance roads in various Wards of Elampalloor Grama Panchayat.-Pipeline Work |
Kottarakkara PH Sn |
|
2 |
Jal jeevan Mission Phase 1 - Providing FHTC , Pipe line Extension and Replacement of Existing AC distribution main in Elampalloor Grama Panchayath |
Kundara PH Sn |
|
3 |
JJM-RWSS to Elampalloor Panchayathu - Replacing old damaged 100 mm CI pipe with 100 mm DI K9 pipe from Punukkannoor old pumphouse to Colony tank |
Kottarakkara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 May 2024 |
Maintenance work |
Kottarakkara PH Sn - AE |
|
27 Apr 2024 |
Leak Work |
Kottarakkara PH Sn - AE |
|
17 Apr 2024 |
Leak rectification |
Kottarakkara PH Sn - AE |
|
13 Apr 2024 |
No work |
Kottarakkara PH Sn - AE |
|
10 Apr 2024 |
No work |
Kottarakkara PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2021 |
Scheduled date of Completion of the Project |
21 Feb 2022 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
31 Aug 2020 |