- Home
- Deposit work-Manalur grama panchayath-Ja...
Deposit work-Manalur grama panchayath-Janakeeyaasoothranam 2019-2020-RWSS to Manalur-Pipe line extension to various wards of Manalur Gramapanchayath.
Project |
Deposit work-Manalur grama panchayath-Janakeeyaasoothranam 2019-2020-RWSS to Manalur-Pipe line extension to various wards of Manalur Gramapanchayath. |
Project Code |
TCRDEPO03208891 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work-Manalur grama panchayath-Janakeeyaasoothranam 2019-2020-RWSS to Manalur-Pipe line extension to various wards of Manalur Grama panchayath.
|
Status |
Completed |
District |
Thrissur |
Executing Office |
Thrissur WW Sn 2 |
AS Amount (Rs) |
1425000
|
AS Number |
Project No 51/21 Lr No A1-1111/16 Vol 2 of EE,PH Division,Thrissur |
TS Amount (Rs) |
1425000 |
TS Number |
TS/2021-2022/2020/28735 Dated: 03-05-2021 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
650 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
18 Aug 2021 |
Coverage |
Manalur panchayat |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work-Manalur gramapanchayath-Janakeeyaasoothranam 2019-2020-RWSS to Manalur-Pipe line extension to various wards of Manalur Gramapanchayath. |
Thrissur WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Nov 2022 |
Work completed. Bill paid |
Thrissur PH Dn EE |
|
13 Jun 2022 |
Completed |
Thrissur WW Sub Dn - AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/07/2021 |
Scheduled date of Completion of the Project |
18 Aug 2021 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
06 Mar 2020 |
TS Date |
05 Mar 2021 |