| Project | Jal Jeevan Mission (JJM) - Kannur District - Mattool GP - JICA WSS to Pattuvam and adjoining villages Phase II - Balance Work - Providing Additional FHTCs |
|---|---|
| Project Code | KNRJJM08202986P2 |
| Type | Package |
| Main Project | Jal Jeevan Mission - Kannur District - Mattool Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission (JJM) - Kannur District - Mattool GP - JICA WSS to Pattuvam and adjoining villages Phase II - Balance Work - Providing Additional FHTCs |
| Status | Completed |
| District | Kannur |
| Executing Office | Kalliassery WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 1860000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/2219/2023_26_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 13 Jul 2023 |
|---|---|
| Estimate Approval | 13 Jul 2023 |
| Tender Closing | 18 Aug 2023 |
| Workorder Date | 13 Sep 2023 |
|---|---|
| NA | 21 Sep 2023 |
| Kalliassery W S Section - AE |
| Date: 19/09/2024 |
Work has been completed | 100% Completed
Work completed.
| Kalliassery W S Section - AE |
| Date: 10/09/2024 |
Work has been completed | 100% Completed
Work completed.