Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Supplying, laying, testing and commissioning of 600 mm DI K9 pipe from Vacherippara Junction to Kizhakkambalam Junction for a lengthy of 1500mtr and 400mm DI K9 pipe from Kizhakkambalam Junction to Thamarachal Junction for a length of 800mtr

Project Supplying, laying, testing and commissioning of 600 mm DI K9 pipe from Vacherippara Junction to Kizhakkambalam Junction for a lengthy of 1500mtr and 400mm DI K9 pipe from Kizhakkambalam Junction to Thamarachal Junction for a length of 800mtr
Project Code EKMGOK08135350P2
Type Package
Main Project 19- Replacement of damaged ac pipes in vazhakkulam,kizhakkambalam & kunnathunadu panchayath
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Supplying, laying, testing and commissioning of 600 mm DI K9 pipe from Vacherippara Junction to Kizhakkambalam Junction for a lengthy of 1500mtr and 400mm DI K9 pipe from Kizhakkambalam Junction to Thamarachal Junction for a length of 800mtr
Status Completed
District Ernakulam
Executing Office Perumbavoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Supplying, laying, testing and commissioning

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/11/2014
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 25/06/2019

Processing Dates

AS Date 03 Aug 2013
TS Date 20 Nov 2013
Estimate Approval 20 Nov 2013
NIT Approval 25 Nov 2013
Tender Closing 31 Jan 2014
Technichal Pre-Qualification 20 Feb 2014
Price bid opening 27 Feb 2014

Approval Dates

Head Office Approval 04 Mar 2014
Workorder Date 04 Mar 2020
NA 21 Mar 2014

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Aluva AEE JJM
Date: 25/11/2020

Work has been completed | 100% Completed

Work completed.