Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-WSS TO adoor and adjoining panchayathu -Replacing of damaged distribution main in pallickal panchayathu

Project KIIFB-WSS TO adoor and adjoining panchayathu -Replacing of damaged distribution main in pallickal panchayathu
Project Code PTAKIIFB04186058
Type Main project
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-WSS TO adoor and adjoining panchayathu -Replacing of damaged distribution main in pallickal panchayathu
Status On-going
District Pathanamthitta
Executing Office Pathanamthitta PH Dn
AS Amount (Rs) 103567000
AS Number APR-4/401/2018/KIIFB
TS Amount (Rs) 103560000
TS Number TS/2020-2021/2018/386
Total Bill Submitted (Rs) 29327222
Total Bill Paid (Rs) 29327222
Population Benefitted 4895
Capacity in MLD 2.50
Actual Project Completion Date 31 Oct 2022
Coverage Adoor HS jn to Pazhakulam in KP road and Pazhakulam to Anayadi in Pazhakulam - Anayadi road ( Pallickal pt)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB - WSS to Adoor and adjoining Panchayaths - Replacing of damaged distribution main in Pallickal Panchayath. Chiranickal Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Mar 2024 Pipe laying works from Pazhakulam Jn. to Adoor High school Jn Chiranickal WS Section - AE
28 Feb 2024 Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done Chiranickal WS Section - AE
24 Feb 2024 Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done Chiranickal WS Section - AE
20 Feb 2024 Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done Chiranickal WS Section - AE
13 Feb 2024 Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done Chiranickal WS Section - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/10/2021
Scheduled date of Completion of the Project 01 Jan 2022
Expected date of Completion 31/03/2023

Processing Dates

AS Date 09 Apr 2018
TS Date 24 Dec 2020

Other details

Project Officers View