- Home
- KIIFB-WSS TO adoor and adjoining panchay...
KIIFB-WSS TO adoor and adjoining panchayathu -Replacing of damaged distribution main in pallickal panchayathu
Project |
KIIFB-WSS TO adoor and adjoining panchayathu -Replacing of damaged distribution main in pallickal panchayathu |
Project Code |
PTAKIIFB04186058 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB-WSS TO adoor and adjoining panchayathu -Replacing of damaged distribution main in pallickal panchayathu
|
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Pathanamthitta PH Dn |
AS Amount (Rs) |
103567000
|
AS Number |
APR-4/401/2018/KIIFB |
TS Amount (Rs) |
103560000 |
TS Number |
TS/2020-2021/2018/386 |
Total Bill Submitted (Rs) |
29327222 |
Total Bill Paid (Rs) |
29327222 |
Population Benefitted |
4895 |
Capacity in MLD |
2.50 |
Actual Project Completion Date |
31 Oct 2022 |
Coverage |
Adoor HS jn to Pazhakulam in KP road and Pazhakulam to Anayadi in Pazhakulam - Anayadi road ( Pallickal pt) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB - WSS to Adoor and adjoining Panchayaths - Replacing of damaged distribution main in Pallickal Panchayath. |
Chiranickal Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Mar 2024 |
Pipe laying works from Pazhakulam Jn. to Adoor High school Jn |
Chiranickal WS Section - AE |
|
28 Feb 2024 |
Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done |
Chiranickal WS Section - AE |
|
24 Feb 2024 |
Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done |
Chiranickal WS Section - AE |
|
20 Feb 2024 |
Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done |
Chiranickal WS Section - AE |
|
13 Feb 2024 |
Pipe laying works from Pazhakulam Jn. to Adoor High school Jn - road restoration work to be done |
Chiranickal WS Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
29/10/2021 |
Scheduled date of Completion of the Project |
01 Jan 2022 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
09 Apr 2018 |
TS Date |
24 Dec 2020 |