Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alapuzha muncipality 6,9

Project AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alapuzha muncipality 6,9
Project Code ALPGOI1117490P1
Type Package
Main Project AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description The Augmentation of water supply scheme to Alappuzha Municipality under under AMRUT is carrying out in 03 phases. In this present estimate comprising for Phase 3 for laying new distribution network in Alappuzha Municipality for Zones 06, 09. The AS for phase 3 is GO(Rt.) No. 3530/2017/LSGD dtd. 02/11/2017 (2017-18) Amount Rs. 5813 lakhs .The work was awarded to ABG Engineering ,muthoor, Thiruvalla vide agreement No 06/2018-19/SE/PHC/ALP dtd 10-08-2018 and the PAC of the work is 34.92crores. The work comprises of laying of 110 mm PVC pipe 8 Kg for 37507m, 160 mm PV C pipe 8 Kg 139655m, 150mmDI K9 PIPE-1669M,200 mm DI K9 pipe-3004m, 250 mm DI K9 pipe-3632m, 300 mm Di K9 pipe-3047m, 350 mm DI K9 pipe-30m, 400 mm DI K9 pipe-1475m, 180 mm HDPE Pipe-1000m, 125 mm HDPE pipe-500m, 250 RCC pipe-150m,100mm to 400mm MS pipe-1220m.
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 340000000
TS Number 2018/285
Technical specification AMRUT ZONE 6&9 pipe laying DI ,PVC MS
Contractor ABG ENGINEERING PVT LTD (Mob: 9446021804)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
15 Nov 2021 Pending Pending Road Cut Related Risk PWD Tarcut permission not obtained for1. Kaithavana- Police Out post2. Kallupalam- Chungam(Thekkekkara) No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/12/2018
Scheduled date of Completion as per agreement 09 Nov 2019
Expected date of Completion 31/12/2022

Processing Dates

TS Date 05 Feb 2018
Estimate Approval 05 Feb 2018
NIT Approval 11 Apr 2018
Tender Closing 11 Apr 2018
Technichal Pre-Qualification 30 Apr 2018
Price bid opening 15 May 2018

Approval Dates

Workorder Date 28 Jul 2018
NA 10 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn PM
Date: 20/05/2024

Work in progress | 98% Completed

Work completed Final bill under processing. .

Alappuzha Project Dn PM
Date: 19/05/2024

Work in progress | 98% Completed

Work completed Final bill under processing. .