AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alapuzha muncipality 6,9
Project |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3-Supplying laying new distribution network in Alapuzha muncipality 6,9 |
Project Code |
ALPGOI1117490P1 |
Type |
Package |
Main Project |
AMRUT-Augmentation& Modernization of water supply distribution system in Alappuzha Municipality-Phase 3
|
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
The Augmentation of water supply scheme to Alappuzha Municipality under under AMRUT is carrying out in 03 phases. In this present estimate comprising for Phase 3 for laying new distribution network in Alappuzha Municipality for Zones 06, 09. The AS for phase 3 is GO(Rt.) No. 3530/2017/LSGD dtd. 02/11/2017 (2017-18) Amount Rs. 5813 lakhs .The work was awarded to ABG Engineering ,muthoor, Thiruvalla vide agreement No 06/2018-19/SE/PHC/ALP dtd 10-08-2018 and the PAC of the work is 34.92crores. The work comprises of laying of 110 mm PVC pipe 8 Kg for 37507m, 160 mm PV C pipe 8 Kg 139655m, 150mmDI K9 PIPE-1669M,200 mm DI K9 pipe-3004m, 250 mm DI K9 pipe-3632m, 300 mm Di K9 pipe-3047m, 350 mm DI K9 pipe-30m, 400 mm DI K9 pipe-1475m, 180 mm HDPE Pipe-1000m, 125 mm HDPE pipe-500m, 250 RCC pipe-150m,100mm to 400mm MS pipe-1220m. |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
340000000 |
TS Number |
2018/285 |
Technical specification |
AMRUT ZONE 6&9 pipe laying DI ,PVC MS |
Contractor |
ABG ENGINEERING PVT LTD (Mob: 9446021804) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
15 Nov 2021 |
Pending |
Pending |
Road Cut Related Risk |
PWD Tarcut permission not obtained for1. Kaithavana- Police Out post2. Kallupalam- Chungam(Thekkekkara) |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
19/12/2018 |
Scheduled date of Completion as per agreement |
09 Nov 2019 |
Expected date of Completion |
31/12/2022 |
Processing Dates
TS Date |
05 Feb 2018 |
Estimate Approval |
05 Feb 2018 |
NIT Approval |
11 Apr 2018 |
Tender Closing |
11 Apr 2018 |
Technichal Pre-Qualification |
30 Apr 2018 |
Price bid opening |
15 May 2018 |
Approval Dates
Workorder Date |
28 Jul 2018 |
NA |
10 Aug 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha Project Dn PM |
Date: 20/05/2024 |
Work in progress | 98% Completed
Work completed Final bill under processing.
.
Alappuzha Project Dn PM |
Date: 19/05/2024 |
Work in progress | 98% Completed
Work completed Final bill under processing.
.