| Project | DEPOSIT-KRFB - Utility shifting in Pathanapuran Post office Junction- Manchaloor-KundayamKaduvathodu-Enath road-Utility shifting in Pathanapuran Post office Junction- ManchaloorKundayam-Kaduvathodu-Enath road-ALTERATION OF HOUSE CONNECTIONS |
|---|---|
| Project Code | KLMDEPO112214532P1 |
| Type | Package |
| Main Project | DEPOSIT-KRFB - Utility shifting in Pathanapuran Post office Junction- Manchaloor-KundayamKaduvathodu-Enath road-Utility shifting in Pathanapuran Post office Junction- ManchaloorKundayam-Kaduvathodu-Enath road-ALTERATION OF HOUSE CONNECTIONS |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Utility shifting in Pathanapuran Post office Junction- Manchaloor-KundayamKaduvathodu-Enath road-Utility shifting in Pathanapuran Post office Junction- ManchaloorKundayam-Kaduvathodu-Enath road-ALTERATION OF HOUSE CONNECTIONS |
| Status | On-going |
| District | Kollam |
| Executing Office | Pathanapuram WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 2896500 |
| TS Number | 16163/2022-2023 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 30/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 29/04/2023 |
| TS Date | 14 Mar 2023 |
|---|---|
| Estimate Approval | 14 Mar 2023 |
| Kottarakkara PH Dn EE |
| Date: 01/12/2023 |
Work has been completed | 100% Completed
Work Completed.