Rebuild Kerala Initiative-Energy Optimization and Replacing 16 inefficient Pumping Systems

Project Rebuild Kerala Initiative-Energy Optimization and Replacing 16 inefficient Pumping Systems
Project Code TVMRKI082212111
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Rebuild Kerala Initiative-Energy Optimization and Replacing 16 inefficient Pumping Systems
Status Completed
District Thiruvananthapuram
Executing Office Head Office
AS Amount (Rs) 67986034
AS Number G.O(Rt) No.299/2022/P&EA
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 31 Mar 2023
Coverage
Implementation Schedule Download

Packages

No. Project Name Location View
1 Automation of submersible pumps in Kerala Water Authority – Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Reserve control module for attending emergencies in Automated pumping stations- RWSS to Alakode-General Electrical Work Head Office
2 Automation of submersible pumps in Kerala Water Authority – Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative – Surveillance mechanism for automated pumping stations – RWSS to Alakode-General Electrical work Head Office
3 JICA Assisted WSS to Pattuvam and adjoining villages-Mace of Intake well cum pump house at Kuyiloor-Supply &fitting 30Kvar power factor capacitor for No.1,2,3,4,5&6 845 HP 3.3 KV VT pump set& 25 Kvar capacitor for 160KVA transformer APFC Panel. Irikkur HW Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Mar 2023 All the three packages are completed Thaliparamba WS Dn EE
10 Apr 2023 JICA Assisted WSS to Pattuvam and adjoining villages-Mace of Intake well cum pump house at Kuyiloor-Supply &fitting 30Kvar power factor capacitor for No.1,2,3,4,5&6 845 HP 3.3 KV VT pump set& 25 Kvar capacitor for 160KVA transformer APFC Panel. ------------------------------- work completed Thaliparamba WS Dn EE
04 Apr 2023 JICA Assisted WSS to Pattuvam and adjoining villages-Mace of Intake well cum pump house at Kuyiloor-Supply &fitting 30Kvar power factor capacitor for No.1,2,3,4,5&6 845 HP 3.3 KV VT pump set& 25 Kvar capacitor for 160KVA transformer APFC Panel. ------------------------------- work completed Thaliparamba WS Dn EE
31 Mar 2023 JICA Assisted WSS to Pattuvam and adjoining villages-Mace of Intake well cum pump house at Kuyiloor-Supply &fitting 30Kvar power factor capacitor for No.1,2,3,4,5&6 845 HP 3.3 KV VT pump set& 25 Kvar capacitor for 160KVA transformer APFC Panel. ------------------------------- work completed Thaliparamba WS Dn EE
28 Mar 2023 JICA Assisted WSS to Pattuvam and adjoining villages-Mace of Intake well cum pump house at Kuyiloor-Supply &fitting 30Kvar power factor capacitor for No.1,2,3,4,5&6 845 HP 3.3 KV VT pump set& 25 Kvar capacitor for 160KVA transformer APFC Panel. ------------- Materials supplied Thaliparamba WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/08/2022
Scheduled date of Completion of the Project 31 May 2023
Expected date of Completion 31/05/2023

Processing Dates

AS Date 02 Aug 2022

Other details

Project Officers View