Automation of submersible pumps in Kerala Water Authority - Implementation of Phase 1(stage 1&2),part under RKI- Surveillance mechanism for automated pumping stations -(Kakkanattukunnu & Muthukulamala pump house under PH section Uzhavoor, Raw water pump house Kummanoor & vattukulangara under PH section Kidangoor, Theradimala pump house at Njeezhoor )

Project Automation of submersible pumps in Kerala Water Authority - Implementation of Phase 1(stage 1&2),part under RKI- Surveillance mechanism for automated pumping stations -(Kakkanattukunnu & Muthukulamala pump house under PH section Uzhavoor, Raw water pump house Kummanoor & vattukulangara under PH section Kidangoor, Theradimala pump house at Njeezhoor )
Project Code KTMRKI042211738
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of submersible pumps in Kerala Water Authority - Implementation of Phase 1(stage 1&2),part under RKI- Surveillance mechanism for automated pumping stations -(Kakkanattukunnu & Muthukulamala pump house under PH section Uzhavoor, Raw water pump house Kummanoor & vattukulangara under PH section Kidangoor, Theradimala pump house at Njeezhoor )
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Dn
AS Amount (Rs) 12440000
AS Number 6296/AE1/(OPERATIONS)/2022/KWA
TS Amount (Rs) 100000
TS Number TS/2022-2023/2022/23110/Dtd:16/06/22
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 950
Capacity in MLD 45.00
Actual Project Completion Date Date is not specified
Coverage Uzhavoor, Njeezhoor and Kidangoor
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Automation of submersible pumps in Kerala Water Authority - Implementation of Phase 1(stage 1&2),part under RKI- Surveillance mechanism for automated pumping stations -(Kakkanattukunnu & Muthukulamala pump house under PH section Uzhavoor,( Uzhavoor PH Sn
2 Automation of submersible pumps in Kerala Water Authority - Implementation of Phase 1(stage 1&2),part under RKI- Surveillance mechanism for automated pumping stations -(Raw water pump house Kummanoor & vattukulangara under PH section Kidangoor) Kidangoor PH Sn
3 Automation of submersible pumps in Kerala Water Authority - Implementation of Phase 1(stage 1&2),part under RKI- Surveillance mechanism for automated pumping stations -( Theradimala pump house at Njeezhoor ) Peruva Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Apr 2024 Bill submitted Kaduthuruthy Dn EE
10 Apr 2024 Bill submitted Kaduthuruthy Dn EE
09 Apr 2024 Bill submitted Kaduthuruthy Dn EE
08 Apr 2024 Bill submitted Kaduthuruthy Dn EE
07 Apr 2024 Bill submitted Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/08/2022
Scheduled date of Completion of the Project 31 Aug 2022
Expected date of Completion 31/08/2022

Processing Dates

AS Date 04 Apr 2022
TS Date 16 Jun 2022

Other details

Project Officers View