Jal Jeevan Mission 2021-22 - CWSS to Perumatty, Pattanchery, Elappully, Nalleppilly Panchayaths in Palakkad district- Phase V- Supplying and laying balance distribution network and providing balance FHTCs (2140 nos) in Elappully Grama Panchayath (Zone- I part II) and road restoration works-

Project Jal Jeevan Mission 2021-22 - CWSS to Perumatty, Pattanchery, Elappully, Nalleppilly Panchayaths in Palakkad district- Phase V- Supplying and laying balance distribution network and providing balance FHTCs (2140 nos) in Elappully Grama Panchayath (Zone- I part II) and road restoration works-
Project Code PKDJJM022212324
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-22 - CWSS to Perumatty, Pattanchery, Elappully,Nalleppilly Panchayaths in Palakkad district- Phase V- Supplying and layingbalance distribution network and providing balance FHTCs (2140 nos) inElappully Grama Panchayath (Zone- I part II) and road restoration works-
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 300000000
AS Number GO (Rt No.134/2022/WRD dtd 23.02.2022
TS Amount (Rs) 112000000
TS Number TS/2022-2023/2021/37818 DTD 05.05.2022
Total Bill Submitted (Rs) 98180554
Total Bill Paid (Rs) 98180554
Population Benefitted
Capacity in MLD
Actual Project Completion Date 18 Jan 2023
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2021-22 - CWSS to Perumatty, Pattanchery, Elappully, Nalleppilly Panchayaths in Palakkad district- Phase V- Supplying and laying balance distribution network and providing balance FHTCs (2140 nos) in Elappully Grama Panchayath (Zone- I part II) and road restoration works- Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Nov 2023 Work in progress | 17% Completed | 24/11/2023 13 LL OHSR-Coloumn concrete first lift above first intermediate slab work in progress Chittur Project Dn - AE 1
06 Sep 2023 Work has been completed | 100% Completed | 06/09/2023 PIPE line laying works and FHTC s work completed except Providing and fixing flow meter and solar pannel work , which can be provided after the construction of 13 LL OHSR AT VETERINARY HOSPITAL COMPOUND. PWD road restoration work completed and , Total pipe supplied and – 95Km pipe laid/out of 95km 1). 90mm HDPE PN 8-65528 m supplied and 65528 laid 2). 90mm HDPE PN 12.50-12060 m supplied and 12060 m laid 3) 80mm GI -17214 m supplied and 17214M laid 4). FHTC- 2235/out of 2140nos 5}600mm DI-81.50 M laid for linking works Chittur Project Dn - AE 1
12 Aug 2023 Work in progress | 98% Completed | 12/08/2023 PIPE line laying works and FHTC s work completed except Providing and fixing flow meter and solar pannel work , which can be provided after the construction of 13 LL OHSR AT VETERINARY HOSPITAL COMPOUND. PWD road restoration work completed and , Total pipe supplied and – 95Km pipe laid/out of 95km 1). 90mm HDPE PN 8-65528 m supplied and 65528 laid 2). 90mm HDPE PN 12.50-12060 m supplied and 12060 m laid 3) 80mm GI -17214 m supplied and 17214M laid 4). FHTC- 2235/out of 2140nos 5}600mm DI-81.50 M laid for linking works Chittur Project Dn - AE 1
03 Aug 2023 Work in progress | 98% Completed | 03/08/2023 PIPE line laying works and FHTC s work completed except Providing and fixing flow meter and solar pannel work , which can be provided after the construction of 13 LL OHSR AT VETERINARY HOSPITAL COMPOUND. PWD road restoration work completed and , Total pipe supplied and – 95Km pipe laid/out of 95km 1). 90mm HDPE PN 8-65528 m supplied and 65528 laid 2). 90mm HDPE PN 12.50-12060 m supplied and 12060 m laid 3) 80mm GI -17214 m supplied and 17214M laid 4). FHTC- 2235/out of 2140nos 5}600mm DI-81.50 M laid for linking works Chittur Project Dn - AE 1
20 Jul 2023 Work in progress | 98% Completed | 20/07/2023 PIPE line laying works and FHTC s work completed except Providing and fixing flow meter and solar pannel work , which can be provided after the construction of 13 LL OHSR AT VETERINARY HOSPITAL COMPOUND. PWD road restoration work completed and , Total pipe supplied and – 95Km pipe laid/out of 95km 1). 90mm HDPE PN 8-65528 m supplied and 65528 laid 2). 90mm HDPE PN 12.50-12060 m supplied and 12060 m laid 3) 80mm GI -17214 m supplied and 17214M laid 4). FHTC- 2235/out of 2140nos 5}600mm DI-81.50 M laid for linking works Chittur Project Dn - AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/07/2022
Scheduled date of Completion of the Project 18 Jan 2023
Expected date of Completion 31/12/2023

Processing Dates

AS Date 23 Feb 2022
TS Date 05 May 2022