- Home
- DEPOSIT-2021-2022-RWSS to (Mylapra- Gram...
DEPOSIT-2021-2022-RWSS to (Mylapra- Grama Panchayath) Replacing of existing 150mm AC distribution pipe from Nalkkalikkalpadi in kumbazha north Nalkkalikkalpadi road-ITC road-Pipeline Work
| Project |
DEPOSIT-2021-2022-RWSS to (Mylapra- Grama Panchayath) Replacing of existing 150mm AC distribution pipe from Nalkkalikkalpadi in kumbazha north Nalkkalikkalpadi road-ITC road-Pipeline Work |
| Project Code |
PTADEPO032213230 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-2021-2022-RWSS to (Mylapra- Grama Panchayath) Replacing of existing 150mm AC distribution pipe from Nalkkalikkalpadi in kumbazha north Nalkkalikkalpadi road-ITC road-Pipeline Work |
| Status |
Completed |
| District |
Pathanamthitta |
| Executing Office |
Pathanamthitta Sn |
| AS Amount (Rs) |
100000
|
| AS Number |
M2/86/2022 |
| TS Amount (Rs) |
98972 |
| TS Number |
TS/11408/2022_26_1_1 |
| Total Bill Submitted (Rs) |
98972 |
| Total Bill Paid (Rs) |
98972 |
| Population Benefitted |
11000 |
| Capacity in MLD |
0.10 |
| Actual Project Completion Date |
15 Jul 2024 |
| Coverage |
Replacing of existing 150mm AC distribution pipe from Nalkkalikkalpadi in kumbazha north Nalkkalikkalpadi road-ITC road-Pipeline Work |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-2021-2022-RWSS to (Mylapra- Grama Panchayath) Replacing of existing 150mm AC distribution pipe from Nalkkalikkalpadi in kumbazha north Nalkkalikkalpadi road-ITC road-Pipeline Work |
Pathanamthitta Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 22 Jul 2024 |
100% of the work has been completed |
Pathanamthitta PH Section - AE |
|
| 09 Jul 2024 |
60% of the work has been completed |
Pathanamthitta PH Section - AE |
|
| 08 Jul 2024 |
90% OF THE WORK HAS BEEN COMPLETED |
Pathanamthitta PH Section - AE |
|
| 22 Dec 2022 |
Agreement Executed on 22.12.2022 |
Pathanamthitta PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
22/12/2022 |
| Scheduled date of Completion of the Project |
23 Jan 2023 |
| Expected date of Completion |
22/07/2023 |
Processing Dates
| AS Date |
14 Mar 2022 |
| TS Date |
05 Nov 2022 |