- Home
- Automation of submersible pumps in Keral...
Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Kidangoor - RWSS to Vattukulangara
Project |
Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Kidangoor - RWSS to Vattukulangara |
Project Code |
KTMRKI03229870 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Kidangoor - RWSS to Vattukulangara
|
Status |
Completed |
District |
Kottayam |
Executing Office |
Kidangoor PH Sn |
AS Amount (Rs) |
20100000
|
AS Number |
6296/AE1(Operations)/2022/KWA |
TS Amount (Rs) |
47000 |
TS Number |
TS/2022-2023/2022/14457 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
400 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
07 May 2022 |
Coverage |
Vattukulangara Area |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Kidangoor - RWSS to Vattukulangara |
Kidangoor PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Jun 2022 |
work completed bill submitted |
Kaduthuruthy Dn EE |
|
01 Jun 2022 |
work completed |
Kaduthuruthy Dn EE |
|
31 May 2022 |
work completed |
Kaduthuruthy Dn EE |
|
28 May 2022 |
work completed |
Kaduthuruthy Dn EE |
|
27 May 2022 |
work completed |
Kaduthuruthy Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/04/2022 |
Scheduled date of Completion of the Project |
27 Apr 2022 |
Expected date of Completion |
30/06/2022 |
Processing Dates
AS Date |
15 Mar 2022 |
TS Date |
12 Apr 2022 |