Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2019-20- RWSS to Kanhangad-replacing old damaged 200 mm Ac distribution main with 200 mm DI K9 pipe(2850m) from Ambalathungara to Chemmattam vayal.

Project State Plan 2019-20- RWSS to Kanhangad-replacing old damaged 200 mm Ac distribution main with 200 mm DI K9 pipe(2850m) from Ambalathungara to Chemmattam vayal.
Project Code KGDGOK06191375
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Replacing old damaged 200 mm Ac distribution main with 200 mm DI K9 pipe(2850m) from Ambalathungara to Chemmattam vayal for Service level improvement
Status On-going
District Kasaragod
Executing Office Kasargod PH Dn
AS Amount (Rs) 10000000
AS Number GO(Rt) No 419/2019/WRD
TS Amount (Rs) 9860000
TS Number TS/2019-2020/2018/12928
Total Bill Submitted (Rs) 5070000
Total Bill Paid (Rs)
Population Benefitted 1000
Capacity in MLD 1.00
Actual Project Completion Date Date is not specified
Coverage Chemmattam vayal
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2019-20- RWSS to Kanhangad-replacing old damaged 200 mm Ac distribution main with 200 mm DI K9 pipe(2850m) from Ambalathungara to Chemmattam vayal.- Package 1 Kanhangad PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Objection raised by the local people to cut the road to lay pipe lines. Hence work pending Kanhangad PH Sn AE
06 May 2024 Objection raised by the local people to cut the road to lay pipe lines. Hence work pending Kanhangad PH Sn AE
30 Apr 2024 Objection raised by the local people to cut the road to lay pipe lines. Hence work pending Kanhangad PH Sn AE
23 Apr 2024 Objection raised by the local people to cut the road to lay pipe lines. Hence work pending Kanhangad PH Sn AE
14 Feb 2024 Objection raised by the local people to cut the road to lay pipe lines. Hence work pending Kanhangad PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/09/2020
Scheduled date of Completion of the Project 14 Dec 2020
Expected date of Completion 30/03/2024

Processing Dates

AS Date 14 Jun 2019
TS Date 05 Jan 2020

Other details

Project Officers View