(JJM)-WSS to Nannambra Grama panchayath in Malappuram District- Package II-Design Construct 9MLD water Treatment Plant with 25.00LL Capacity OHSR ,3.5LL Capacity sump cum pump house, Compound wall including supply and erection of Raw water ,Clear water pump set with transformers and allied works

Project (JJM)-WSS to Nannambra Grama panchayath in Malappuram District- Package II-Design Construct 9MLD water Treatment Plant with 25.00LL Capacity OHSR ,3.5LL Capacity sump cum pump house, Compound wall including supply and erection of Raw water ,Clear water pump set with transformers and allied works
Project Code MLPJJM052213995P2
Type Package
Main Project Jal Jeevan Mission (JJM)-WSS to Nannambra Grama panchayath in Malappuram District-Package 1-Construction of Intake Well cum Pump house, Supply laying Raw water transmission main ,Service reservoirs, including supply Laying distribution system with FHTC -General Civil Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description (JJM)-WSS to Nannambra Grama panchayath in Malappuram District- Package II-Design Construct 9MLD water Treatment Plant with 25.00LL Capacity OHSR ,3.5LL Capacity sump cum pump house, Compound wall including supply and erection of Raw water ,Clear water pump set with transformers and allied works
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 160500000
TS Number WRD/KWA-CEP/EST_TS/20/2022_26_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 07 May 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 29 Mar 2023

Approval Dates

NA 25 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malapuram Proj Dn AE 4
Date: 03/07/2025

Work in progress | 32% Completed

No work .

Malapuram Proj Dn AE 4
Date: 02/07/2025

Work in progress | 32% Completed

No work .