- Home
- Deposit work of Tvpm corporation-Project...
Deposit work of Tvpm corporation-Project no-S0053/20- Providing non domestic connection to the High tech Toilet Block in Medical college block from the existing water connection of Corporation Rest House , ulloor in Pattom ward under Kowdiar section
Project |
Deposit work of Tvpm corporation-Project no-S0053/20- Providing non domestic connection to the High tech Toilet Block in Medical college block from the existing water connection of Corporation Rest House , ulloor in Pattom ward under Kowdiar section |
Project Code |
TVMDEPO07218915 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Tvpm corporation-Project no-S0053/20- Providing non domestic connection to the High tech Toilet Block in Medical college block from the existing water connection of Corporation Rest House , ulloor in Pattom ward under Kowdiar section |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kowdiar WW North Sub Dn |
AS Amount (Rs) |
39000
|
AS Number |
J4/S0053/20 |
TS Amount (Rs) |
39000 |
TS Number |
TS/2021-2022/2021/36349 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
Date is not specified |
Coverage |
High tech Toilet Block in Medical college block |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Tvpm corporation-Project no-S0053/20- Providing non domestic connection to the High tech Toilet Block in Medical college block from the existing water connection of Corporation Rest House , ulloor in Pattom ward under Kowdiar section |
Kowdiar WW North Sub Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Feb 2022 |
100 % works completed. |
Thiruvananthapuram PH Dn (N) - EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/10/2021 |
Scheduled date of Completion of the Project |
31 Oct 2021 |
Expected date of Completion |
08/11/2021 |
Processing Dates
AS Date |
22 Jul 2021 |
TS Date |
09 Feb 2022 |