PACKAGE VI- CONSTRUCTION OF 13.5 LL CAPACITY OHSR AT CHOKLI GOVT.COLLEGE , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs in CHOKLI GRAMA PANCHAYATH

Project PACKAGE VI- CONSTRUCTION OF 13.5 LL CAPACITY OHSR AT CHOKLI GOVT.COLLEGE , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs in CHOKLI GRAMA PANCHAYATH
Project Code KNRJJM022213306P6
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 13.5 LL OHSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 553400000
TS Number WRD/KWA-CE(NR)/EST_TS/3841/2022_26_1_1
Technical specification Construction of13.5 LL OHSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs
Contractor Baburaj P K (Mob: 9447152707)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/08/2023
Scheduled date of Completion as per agreement 31 Jul 2024
Expected date of Completion 31/12/2025

Processing Dates

TS Date 22 Sep 2022
Estimate Approval 22 Sep 2022
NIT Approval 02 Dec 2022
Tender Closing 17 Apr 2023
Technichal Pre-Qualification 02 Dec 2022
Price bid opening 19 Apr 2023

Approval Dates

Workorder Date 27 Jun 2023
NA 24 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 05/01/2026

Work in progress | 60% Completed

Total distribution 234.362 km, in that pipe required is 207.902 km. Out of this 186 km pipe laying completed. House connection work is in progress, 6170 nos. HTC completed. 13.5 LL OHSR Soil study conducted and report obtained from GEC Kannur on 19/05/25.Proposed 13.5 LL GLSR has to be changed to 13.5 LL OHSR.RE and Revised design in progress. Road restoration work under progress.12km (PWD) & 11 km LSGD completed..

Mattannur Project Sn 2 AE
Date: 30/12/2025

Work in progress | 60% Completed

Total distribution 234.362 km, in that pipe required is 207.902 km. Out of this 186 km pipe laying completed. House connection work is in progress, 6170 nos. HTC completed. 13.5 LL OHSR Soil study conducted and report obtained from GEC Kannur on 19/05/25.Proposed 13.5 LL GLSR has to be changed to 13.5 LL OHSR.RE and Revised design in progress. Road restoration work under progress.13km (PWD) & 1km LSGD completed..