PACKAGE VI- CONSTRUCTION OF 13.5 LL CAPACITY GLSR AT CHOKLI GOVT.COLLEGE , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs in CHOKLI GRAMA PANCHAYATH

Project PACKAGE VI- CONSTRUCTION OF 13.5 LL CAPACITY GLSR AT CHOKLI GOVT.COLLEGE , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs in CHOKLI GRAMA PANCHAYATH
Project Code KNRJJM022213306P6
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 13.5 LL GLSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 553400000
TS Number WRD/KWA-CE(NR)/EST_TS/3841/2022_26_1_1
Technical specification Construction of 13.5 LL GLSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs
Contractor Baburaj P K (Mob: 9447152707)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/08/2023
Scheduled date of Completion as per agreement 31 Jul 2024
Expected date of Completion 31/12/2025

Processing Dates

TS Date 22 Sep 2022
Estimate Approval 22 Sep 2022
NIT Approval 02 Dec 2022
Tender Closing 17 Apr 2023
Technichal Pre-Qualification 02 Dec 2022
Price bid opening 19 Apr 2023

Approval Dates

Workorder Date 27 Jun 2023
NA 24 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 59% Completed

EARTH EXCAVATION AND PIPE LAYING IS ON PROGRESS. Total distribution 234.362 km, in that 234.362 km pipe has supplied. Out of this 185.82 km pipe laying completed. House connection work is in progress, 5790 nos. HTC completed. Proposed new Tank site location, soil investigation and testing completed, report received and submitted to GEC Kannur for detailed study report. Road restoration work under progress, 3km completed.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 59% Completed

EARTH EXCAVATION AND PIPE LAYING IS ON PROGRESS. Total distribution 234.362 km, in that 234.362 km pipe has supplied. Out of this 185.82 km pipe laying completed. House connection work is in progress, 5760 nos. HTC completed. Proposed new Tank site location, soil investigation and testing completed, report received and submitted to GEC Kannur for detailed study report. Road restoration work under progress. 3km completed.