| Project | PACKAGE VI- CONSTRUCTION OF 13.5 LL CAPACITY OHSR AT CHOKLI GOVT.COLLEGE , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs in CHOKLI GRAMA PANCHAYATH |
|---|---|
| Project Code | KNRJJM022213306P6 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 13.5 LL OHSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 553400000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/3841/2022_26_1_1 |
| Technical specification | Construction of13.5 LL OHSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs |
| Contractor | Baburaj P K (Mob: 9447152707) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/08/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 31 Jul 2024 |
| Expected date of Completion | 31/12/2025 |
| TS Date | 22 Sep 2022 |
|---|---|
| Estimate Approval | 22 Sep 2022 |
| NIT Approval | 02 Dec 2022 |
| Tender Closing | 17 Apr 2023 |
| Technichal Pre-Qualification | 02 Dec 2022 |
| Price bid opening | 19 Apr 2023 |
| Workorder Date | 27 Jun 2023 |
|---|---|
| NA | 24 Jul 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 60% Completed
Total distribution 234.362 km, in that pipe required is 207.902 km. Out of this 186 km pipe laying completed. House connection work is in progress, 6170 nos. HTC completed. 13.5 LL OHSR Soil study conducted and report obtained from GEC Kannur on 19/05/25.Proposed 13.5 LL GLSR has to be changed to 13.5 LL OHSR.RE and Revised design in progress. Road restoration work under progress.12km (PWD) & 11 km LSGD completed..
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 60% Completed
Total distribution 234.362 km, in that pipe required is 207.902 km. Out of this 186 km pipe laying completed. House connection work is in progress, 6170 nos. HTC completed. 13.5 LL OHSR Soil study conducted and report obtained from GEC Kannur on 19/05/25.Proposed 13.5 LL GLSR has to be changed to 13.5 LL OHSR.RE and Revised design in progress. Road restoration work under progress.13km (PWD) & 1km LSGD completed..