Project | PACKAGE VI- CONSTRUCTION OF 13.5 LL CAPACITY GLSR AT CHOKLI GOVT.COLLEGE , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs in CHOKLI GRAMA PANCHAYATH |
---|---|
Project Code | KNRJJM022213306P6 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 13.5 LL GLSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 553400000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/3841/2022_26_1_1 |
Technical specification | Construction of 13.5 LL GLSR at Chokli Govt.College kunnu, Laying distribution system and providing 6211 Nos FHTCs |
Contractor | Baburaj P K (Mob: 9447152707) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 31 Jul 2024 |
Expected date of Completion | 31/12/2025 |
TS Date | 22 Sep 2022 |
---|---|
Estimate Approval | 22 Sep 2022 |
NIT Approval | 02 Dec 2022 |
Tender Closing | 17 Apr 2023 |
Technichal Pre-Qualification | 02 Dec 2022 |
Price bid opening | 19 Apr 2023 |
Workorder Date | 27 Jun 2023 |
---|---|
NA | 24 Jul 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 59% Completed
EARTH EXCAVATION AND PIPE LAYING IS ON PROGRESS. Total distribution 234.362 km, in that 234.362 km pipe has supplied. Out of this 185.82 km pipe laying completed. House connection work is in progress, 5790 nos. HTC completed. Proposed new Tank site location, soil investigation and testing completed, report received and submitted to GEC Kannur for detailed study report. Road restoration work under progress, 3km completed.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 59% Completed
EARTH EXCAVATION AND PIPE LAYING IS ON PROGRESS. Total distribution 234.362 km, in that 234.362 km pipe has supplied. Out of this 185.82 km pipe laying completed. House connection work is in progress, 5760 nos. HTC completed. Proposed new Tank site location, soil investigation and testing completed, report received and submitted to GEC Kannur for detailed study report. Road restoration work under progress. 3km completed.