- Home
- Deposit work of Kasaragod Municipality-...
Deposit work of Kasaragod Municipality- Pipeline extension to Hashim Street
Project |
Deposit work of Kasaragod Municipality- Pipeline extension to Hashim Street |
Project Code |
KGDDEPO11218297 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Pipeline extension to Hashim Street |
Status |
Completed |
District |
Kasaragod |
Executing Office |
Kasargod PH Dn |
AS Amount (Rs) |
1200000
|
AS Number |
P2-9543/2021 |
TS Amount (Rs) |
1200000 |
TS Number |
16579/2021-2022 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
12 May 2022 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Kasaragod Municipality- Pipeline extension to Hashim Street |
Kasargod WSP Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
work completed on 12/05/2022 |
Kasargod WSP Sn AE |
|
09 May 2024 |
work completed on 12/05/2022 |
Kasargod WSP Sn AE |
|
07 May 2024 |
work completed on 12/05/2022 |
Kasargod WSP Sn AE |
|
22 Apr 2024 |
work completed on 12/05/2022 |
Kasargod WSP Sn AE |
|
17 Apr 2024 |
work completed on 12/05/2022 |
Kasargod WSP Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
14 May 2022 |
Expected date of Completion |
14/05/2022 |
Processing Dates
AS Date |
08 Nov 2021 |
TS Date |
31 Dec 2021 |