- Home
- Stateplan-2021-22-WSS to Anjarakandy, Pe...
Stateplan-2021-22-WSS to Anjarakandy, Peralassery and adjoining Panchayaths-Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath
Project |
Stateplan-2021-22-WSS to Anjarakandy, Peralassery and adjoining Panchayaths-Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath |
Project Code |
KNRGOK08218283 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur WS Dn |
AS Amount (Rs) |
13100000
|
AS Number |
KWA/JB/State Plan/NR/06/2021(I) |
TS Amount (Rs) |
13100000 |
TS Number |
TS/2021-2022/2021/35986 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
5000 |
Capacity in MLD |
46.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Stateplan-2021-22-WSS to Anjarakandy, Peralassery and adjoining Panchayaths-Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath |
Perlassery Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 May 2024 |
No response received, tender cancelled. Estimate to be re casted. |
Perlassery Sn 2 AE |
|
03 May 2024 |
No response received, tender cancelled. Estimate to be re casted. |
Kannur PH Dn EE |
|
25 Apr 2024 |
No response received, tender cancelled. Estimate to be re casted. |
Perlassery Sn 2 AE |
|
25 Apr 2024 |
No response received, tender cancelled. Estimate to be re casted. |
Kannur PH Dn EE |
|
18 Apr 2024 |
No response received, tender cancelled. Estimate to be re casted. |
Perlassery Sn 2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
30/06/2022 |
Processing Dates
AS Date |
24 Aug 2021 |
TS Date |
02 Mar 2022 |