Stateplan-2021-22-WSS to Anjarakandy, Peralassery and adjoining Panchayaths-Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath

Project Stateplan-2021-22-WSS to Anjarakandy, Peralassery and adjoining Panchayaths-Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath
Project Code KNRGOK08218283
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath
Status Dropped
District Kannur
Executing Office Perlassery Sn 2
AS Amount (Rs) 13100000
AS Number KWA/JB/State Plan/NR/06/2021(I)
TS Amount (Rs) 13100000
TS Number TS/2021-2022/2021/35986
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 5000
Capacity in MLD 46.00
Actual Project Completion Date Date is not specified
Coverage Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath

Packages

No. Project Name Location View
1 Stateplan-2021-22-WSS to Anjarakandy, Peralassery and adjoining Panchayaths-Replacement of old AC distribution main line from Moonnuperiya to Keezhara in Peralassery Panchayath Perlassery Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Oct 2024 No response received, tender cancelled. Estimate to be re casted. Perlassery Sn 2 AE
15 Oct 2024 No response received, tender cancelled. Estimate to be re casted. Perlassery Sn 2 AE
08 Oct 2024 No response received, tender cancelled. Estimate to be re casted. Perlassery Sn 2 AE
04 Oct 2024 No response received, tender cancelled. Estimate to be re casted. Perlassery Sn 2 AE
30 Sep 2024 No response received, tender cancelled. Estimate to be re casted. Perlassery Sn 2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 30/06/2022

Processing Dates

AS Date 24 Aug 2021
TS Date 02 Mar 2022

Other details

Project Officers View