AMRUT- 1.0new-Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy -Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy-General Civil Work

Project AMRUT- 1.0new-Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy -Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy-General Civil Work
Project Code EKMAMRUT012415607P1
Type Package
Main Project AMRUT- 1.0new-Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy -Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy-General Civil Work
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT- 1.0new-Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy -Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy-General Civil Work
Status On-going
District Ernakulam
Executing Office Vytilla Head works
Agreement Number
Agreement Date
TS Amount (Rs) 5400000
TS Number TS/22889/2023_5_1_1 Dated: 04-01-2024
Technical specification AMRUT- 1.0-Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy -Interconnecting the existing 1100mm MS and 800mm DI at Thevara for improving Water Supply to Palluruthy-General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/02/2024
Scheduled date of Completion as per agreement 11 Aug 2024
Expected date of Completion 11/08/2024

Processing Dates

TS Date 04 Jan 2024
Estimate Approval 03 Jan 2024
NIT Approval 09 Jan 2024
Tender Closing 18 Jan 2024
Technichal Pre-Qualification 18 Jan 2024
Price bid opening 19 Jan 2024

Approval Dates

Workorder Date 09 Feb 2024
NA 12 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vytilla HW AE
Date: 19/03/2024

Work has been completed | 100% Completed

Work completed and final bill submitted.

Vytilla HW AE
Date: 18/03/2024

Work in progress | 95% Completed

Part bill submitted.