AMRUT SAAP 2017-18- WSS to Palakkad Municipality - Phase III - Package I - Replacement of raw water and clear water pump set and electrification, Constuction of OHSR 2 Nos
Project |
AMRUT SAAP 2017-18- WSS to Palakkad Municipality - Phase III - Package I - Replacement of raw water and clear water pump set and electrification, Constuction of OHSR 2 Nos |
Project Code |
PKDAMRUT1217687 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Constuction of OHSR 2 Nos , total 60.5LL capacity,
Replacement of raw water and clear water pump set, transformers and electrification
|
Status |
Completed |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
138600000
|
AS Number |
4165/2017/LSGD |
TS Amount (Rs) |
138600000 |
TS Number |
KWA/CE/NR/36/17 |
Total Bill Submitted (Rs) |
122527768 |
Total Bill Paid (Rs) |
122527768 |
Population Benefitted |
172683 |
Capacity in MLD |
45.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Palakkad muncipality Moothanthara and Mattumantha |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT SAAP 2017-18- Palakkad WSS - Phase III - Package I - Constuction of OHSR 2 Nos |
Project Division Palakkad |
|
2 |
AMRUT SAAP 2017-18- Palakkad WSS - Phase III - Package I -Replacement of raw water and clear water pump set and electrification |
Project Division Palakkad |
|
3 |
AMRUT SAAP 2017-18- Phase II - shifting of 630 KVA transformer from 9 MLD WTP CW Sump compound to Clear Water Sump cum pumphouse of 45 MLD WTP and erection of main switch board and energizing |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Jun 2022 |
All works completed |
Palakkad Proj Dn AE 4 |
|
28 May 2022 |
Clear Water pump erection works finished. Trial Run in progress * Raw Water pump set erection works progressing. 2 pumps erected trial run progressing * OHSRs works completed |
Palakkad Proj Dn AE 4 |
|
27 May 2022 |
Clear Water pump erection works finished. Trial Run in progress * Raw Water pump set erection works progressing. 2 pumps erected trial run progressing * OHSRs works completed |
Palakkad Proj Dn AE 4 |
|
26 May 2022 |
Clear Water pump erection works finished. Trial Run in progress * Raw Water pump set erection works progressing. 2 pumps erected trial run progressing * OHSRs works completed |
Palakkad Proj Dn AE 4 |
|
25 May 2022 |
Clear Water pump erection works finished. Trial Run in progress * Raw Water pump set erection works progressing. 2 pumps erected trial run progressing * OHSRs works completed |
Palakkad Proj Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
29/05/2018 |
Scheduled date of Completion of the Project |
28 May 2019 |
Expected date of Completion |
20/05/2022 |
Processing Dates
AS Date |
23 Dec 2017 |
TS Date |
09 Jan 2018 |