Jal Jeevan Mission (JJM)-Panniyannur Grama Panchayth-Road Reformation on PWD Roads-Balance .-WSS to Panniyannur,Panoor and Mokeri-PhaseIII--Road Reformation on PWD Roads and shifting connections --Pipeline Work

Project Jal Jeevan Mission (JJM)-Panniyannur Grama Panchayth-Road Reformation on PWD Roads-Balance .-WSS to Panniyannur,Panoor and Mokeri-PhaseIII--Road Reformation on PWD Roads and shifting connections --Pipeline Work
Project Code KNRJJM102316198P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Panniyannur Grama Panchayth-Road Reformation on PWD Roads-Balance .-WSS to Panniyannur,Panoor and Mokeri-PhaseIII--Road Reformation on PWD Roads and shifting connections --Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Panniyannur Grama Panchayth Re appropriation-Road Reformation on PWD Roads-Balance .-WSS to Panniyannur,Panoor and Mokeri-PhaseIII--Road Reformation on PWD Roads and shifting connections --Pipeline Work
Status On-going
District Kannur
Executing Office Thalassery PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 204
TS Number 22248/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 21 Jul 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 18 Dec 2023

Approval Dates

Workorder Date 13 Feb 2024
NA 12 Mar 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thalassery PH Sn AE
Date: 26/10/2024

Work has started | 0% Completed

work can be started only after the pipe laying works are completed..

Thalassery PH Sn AE
Date: 27/09/2024

Work has started | 0% Completed

work can be started only after the pipe laying works are completed..