Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State plan 2021-22-Optimization of production and Transmission - Replacement of old pipes in existing WSS - Replacing damaged 250mm PVC from Eranhippalam junction to Arayadathupalam junction along mini bypass road for a length of 3000m.

Project State plan 2021-22-Optimization of production and Transmission - Replacement of old pipes in existing WSS - Replacing damaged 250mm PVC from Eranhippalam junction to Arayadathupalam junction along mini bypass road for a length of 3000m.
Project Code CLTGOK06217954
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Replacing damaged 250mm PVC from Eranhippalam junction to Arayadathupalam junction along mini bypass road for a length of 3000m.
Status On-going
District Kozhikkode
Executing Office Kozhikode PH Dn
AS Amount (Rs) 15070000
AS Number KWA/JB/PIU-1/AE4/STATEPLAN/OPT/05/21-22(IV)
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 State plan 2021-22-Optimization of production and Transmission - Replacement of old pipes in existing WSS - Replacing damaged 250mm PVC from Eranhippalam junction to Arayadathupalam junction along mini bypass road for a length of 3000m. Kozhikode Dist 2 Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Feb 2024 Included in Amrut 1.0 Kozhikode PH Dn EE
17 Jan 2024 Included in Amrut 1.0 Kozhikode PH Dn EE
20 Nov 2023 tender cancelled Kozhikode PH Dn EE
12 Jul 2023 tender cancelled Kozhikode PH Dn EE
05 Jul 2023 The contractor has quoted the work 41% above on TPAC, The tender committee approved the single tender with 10% excess on TPAC, but the contractor is not willing to execute the work on the approved rate. Hence tender cancelled Kozhikode PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 28/09/2023

Processing Dates

AS Date 16 Jun 2021

Other details

Project Officers View