Project | 22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths. Supply, erection, testing and commissioning of 20HP CP Motor pumpsets for a total head of 67.65m and discharge of 10 lps for sump cum pump house at Varakkara and power allocation charges. |
---|---|
Project Code | TCRNABARD05168175P1 |
Type | Package |
Main Project | 22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths. Supply, erection, testing and commissioning of 20HP CP Motor pumpsets for a total head of 67.65m and discharge of 10 lps for sump cum pump house at Varakkara and power allocation charges. |
Funding Agency | NABARD |
Category | NABARD |
Type of scheme | Water Supply |
Scheme | |
Description | 22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths. Supply, erection, testing and commissioning of 20HP CP Motor pumpsets for a total head of 67.65m and discharge of 10 lps for sump cum pump house at Varakkara and power allocation charges. |
Status | Completed |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 990000 |
TS Number | TS/CE/CR/KWA/09/2015-16 |
Technical specification | |
Contractor | Rahul P Mathew (Mob: 8547468444) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/03/2019 |
---|---|
Scheduled date of Completion as per agreement | 06 Apr 2019 |
Expected date of Completion | 26/03/2019 |
TS Date | 04 Nov 2015 |
---|---|
Estimate Approval | 04 Nov 2015 |
NIT Approval | 04 Nov 2015 |
Workorder Date | 05 Feb 2019 |
---|---|
NA | 07 Feb 2019 |
Nattika AE 3 |
Date: 16/11/2021 |
Work has been completed | 100% Completed
Erection work completed on 26.03.2019.