- Home
- [ WRD/KWA-CE(NR)/EST/13952/2024_5_1_1 ]...
[ WRD/KWA-CE(NR)/EST/13952/2024_5_1_1 ] Others-Development of Taluk hospital, Iritty in Kannur District, Kerala state for Health and Family Welfare Department Govt. of Kerala-- Rerouting of existing KWA water lines through project site. -General Civil Work
Project |
[ WRD/KWA-CE(NR)/EST/13952/2024_5_1_1 ] Others-Development of Taluk hospital, Iritty in Kannur District, Kerala state for Health and Family Welfare Department Govt. of Kerala-- Rerouting of existing KWA water lines through project site. -General Civil Work |
Project Code |
KNRDEPO082417123 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
The existing KWA lines are the important lines to supply portable water to Taluk Hospital and Narikkundam colony. Development of Taluk Hospital, Iritty in Kannur District for Health & Family Welfare Department has decided to construct new structure in the hospital premise where KWA line exists.During construction these live lines may be disturbed and chance of getting collapse in regular water supply isturbing these lines. Hence before starting the construction work entire lines should be re-laid. Informations has already been given to consultancy that. All these line are the existing asset of KWA and relaying/rerouting should be done at their own cost.
Now there are three lines in that premise. Out of three, two lines are KWA distribution lines.Hence estimate has been prepared for relaying two live KWA Lines. |
Status |
Completed |
District |
Kannur |
Executing Office |
Mattannur PH Sub Dn |
AS Amount (Rs) |
181000
|
AS Number |
CW/H&FWD/KIIFB/ITY/2024 |
TS Amount (Rs) |
181000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/13952/2024_5_1_1 |
Total Bill Submitted (Rs) |
148863 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
24 Jan 2025 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Others-Development of Taluk hospital, Iritty in Kannur District, Kerala state for Health and Family Welfare Department Govt. of Kerala-- Rerouting of existing KWA water lines through project site. -General Civil Work |
Mattannur PH Sub Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Feb 2025 |
Work completed,final bill submitted |
Mattannur PH Sub-Dn - AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
07/12/2024 |
Scheduled date of Completion of the Project |
06 Mar 2025 |
Expected date of Completion |
21/01/2025 |
Processing Dates
AS Date |
27 Aug 2024 |
TS Date |
10 Sep 2024 |