MLA - ADS - 2020-21 - Vattiyoorkavu Constituency - TSS - Replacing of old and damaged 150 mm SW sewer line with 300 mm SW sewer line near Sreekrishna Swami Temple, Ambalamukku, under Sewerage Section, Sasthamangalam
Project |
MLA - ADS - 2020-21 - Vattiyoorkavu Constituency - TSS - Replacing of old and damaged 150 mm SW sewer line with 300 mm SW sewer line near Sreekrishna Swami Temple, Ambalamukku, under Sewerage Section, Sasthamangalam |
Project Code |
TVMDC-LAC/ADS/SDF/KSCADC08203148 |
Type |
Main project |
Funding Agency |
DC-LAC/ADS/SDF/KSCADC |
Category |
MLA ADS |
Type of scheme |
Water Supply |
Scheme |
DC-LAC/ADS/SDF/KSCADC |
Description |
MLA - ADS - 2020-21 - Vattiyoorkavu Constituency - TSS - Replacing of old and damaged 150 mm SW sewer line with 300 mm SW sewer line near Sreekrishna Swami Temple, Ambalamukku, under Sewerage Section, Sasthamangalam
AS:-D1-2090/20 dated 22.01.2021 DC, TVM |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Sasthamangalam Sewerage Sn |
AS Amount (Rs) |
4246000
|
AS Number |
D1-2090/20 |
TS Amount (Rs) |
3921000 |
TS Number |
14519/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
MLA - ADS - 2020-21 - Vattiyoorkavu Constituency - TSS - Replacing of old and damaged 150 mm SW sewer line with 300 mm SW sewer line near Sreekrishna Swami Temple, Ambalamukku, under Sewerage Section, Sasthamangalam
AS:-D1-2090/20 dated 22.01.2021 DC, TVM |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
MLA - ADS - 2020-21 - Vattiyoorkavu Constituency - TSS - Replacing of old and damaged 150 mm SW sewer line with 300 mm SW sewer line near Sreekrishna Swami Temple, Ambalamukku, under Sewerage Section, Sasthamangalam |
Sasthamangalam Sewerage Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Feb 2023 |
inter lock relaying completed |
Sasthamangalam Sewerage Sn AE |
|
22 Feb 2023 |
inter lock relaying progress |
Sasthamangalam Sewerage Sn AE |
|
20 Feb 2023 |
inter lock relaying progress |
Sasthamangalam Sewerage Sn AE |
|
14 Feb 2023 |
road formation progress |
Sasthamangalam Sewerage Sn AE |
|
07 Feb 2023 |
300mm sw pipe (129/129) laying completed and Seventh manhole (7/7)construction completed |
Sasthamangalam Sewerage Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
05/02/2022 |
Scheduled date of Completion of the Project |
04 Jul 2022 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
22 Jan 2021 |
TS Date |
02 Dec 2021 |