Jal Jeevan Mission (JJM)-WSS to Anjrakandy,Peralassery and adjoining panchayath--Providing FHTC by PWD road crossing/cutting in Kadirur panchayath-Balance Work-2-Pipeline Work

Project Jal Jeevan Mission (JJM)-WSS to Anjrakandy,Peralassery and adjoining panchayath--Providing FHTC by PWD road crossing/cutting in Kadirur panchayath-Balance Work-2-Pipeline Work
Project Code KNRJJM08302937P10
Type Package
Main Project JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassery and adjoining panchayaths-Phase II.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-WSS to Anjrakandy,Peralassery and adjoining panchayath--Providing FHTC by PWD road crossing/cutting in Kadirur panchayath-Balance Work-2-Pipeline Work
Status On-going
District Kannur
Executing Office Perlassery Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 2420000
TS Number Jal Jeevan Mission (JJM)-WSS to Anjrakandy,Peralassery and adjoining panchayath--Providing FHTC by PWD road crossing/cutting in Kadirur panchayath-Balance Work-2-Pipeline Work
Technical specification Providing FHTC by PWD road crossing/cutting in Kadirur panchayath
Contractor CHANDRAN ALAKKATT (Mob: 9447550036)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/03/2024
Scheduled date of Completion as per agreement 26 Sep 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 04 Mar 2024
Estimate Approval 04 Mar 2024
NIT Approval 04 Mar 2024
Tender Closing 27 Jul 2024
Technichal Pre-Qualification 29 Jul 2024
Price bid opening 29 Jul 2024

Approval Dates

Workorder Date 14 Aug 2024
NA 27 Aug 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Perlasserry Sn 1
Date: 25/04/2026

Work in progress | 95% Completed

100 nos of FHTCs proposed.95 nos of FHTCs given..

Perlasserry Sn 1
Date: 18/04/2026

Work in progress | 95% Completed

100 nos of FHTCs proposed.95 nos of FHTCs given..