- Home
- KIIFB- WSS to Kodassery, Pariyaram and A...
KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District
Project |
KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District |
Project Code |
TCRKIIFB1118498 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Package-1
a) 9m dia Intake well cum pump house at Vettilappara
b) Raw water pumpset-330 HP -2 Nos
c) RWPM 450mm DI K9-4900m
d)12 MLD WTP at Pillappara
e) 2LL OHSR for Athirapilly GP
f) Clear water pumpset at Athirapilly- 7.5HP-2Nos
g) 150mm CWPM to Athirapilly Tank -50m
h) 450mm DI K9 CWGM from WTP to 1st Common Junction (Vettikuzhy)-10230M
i) 500kVA Transformer at Intakewell site
j)100 kVA Transformer at WTP site
k) Crane facility, SCADA
l) Site leveling & Retaining wall at WTP site
m) Road restoration works
******
Package-2
a) 20LL OHSR at Chembankunnu (Kodassery GP Low Level)
b) 1LL OHSR at Chaipankuzhy (Kodassery GP High Level)
c) 14LL OHSR at Orappana (Pariyaram GP)
d) 250mm DI K9 CWGM from 1st Common Junction to 20LL OHSR- 2100m
e) 350mm DI K9 CWGM from 1st Common Junction to 2nd Common Junction (Peelarmuzhy Anganvadi) - 1500M
f) 250mm DI K9 CWGM from 2nd Common Junction to 14LL OHSR-7340m
g) 100mm DI K9 CWPM from 2nd Common Junction to 1LL OHSR-370m
h) Booster pump house with 5HP Booster pump set at Peelarmuzhy Anganvadi
i) Road restoration works |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
586100000
|
AS Number |
WRD025-03-PA-01 Dated: 13.11.2018 |
TS Amount (Rs) |
586100000 |
TS Number |
TS/2019-2020/2019/17186, 17187 Dated: 22.11.2019 |
Total Bill Submitted (Rs) |
196416508 |
Total Bill Paid (Rs) |
196416508 |
Population Benefitted |
80500 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Kodassery, Pariyaram and Athirappilly panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District-Package 1 |
Nattika Project Dn |
|
2 |
KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District- Package-2 |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 May 2024 |
Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.404/3.7 KM |
Nattika AE 3 |
|
05 May 2024 |
Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.384/3.7 KM |
Nattika AE 3 |
|
04 May 2024 |
Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.384/3.7 KM |
Nattika AE 3 |
|
03 May 2024 |
Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.318/3.7 KM |
Nattika AE 3 |
|
02 May 2024 |
Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.318/3.7 KM |
Nattika AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/07/2020 |
Scheduled date of Completion of the Project |
28 Jun 2022 |
Expected date of Completion |
14/09/2024 |
Processing Dates
AS Date |
13 Nov 2018 |
TS Date |
22 Nov 2019 |