KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District

Project KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District
Project Code TCRKIIFB1118498
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Package-1 a) 9m dia Intake well cum pump house at Vettilappara b) Raw water pumpset-330 HP -2 Nos c) RWPM 450mm DI K9-4900m d)12 MLD WTP at Pillappara e) 2LL OHSR for Athirapilly GP f) Clear water pumpset at Athirapilly- 7.5HP-2Nos g) 150mm CWPM to Athirapilly Tank -50m h) 450mm DI K9 CWGM from WTP to 1st Common Junction (Vettikuzhy)-10230M i) 500kVA Transformer at Intakewell site j)100 kVA Transformer at WTP site k) Crane facility, SCADA l) Site leveling & Retaining wall at WTP site m) Road restoration works ****** Package-2 a) 20LL OHSR at Chembankunnu (Kodassery GP Low Level) b) 1LL OHSR at Chaipankuzhy (Kodassery GP High Level) c) 14LL OHSR at Orappana (Pariyaram GP) d) 250mm DI K9 CWGM from 1st Common Junction to 20LL OHSR- 2100m e) 350mm DI K9 CWGM from 1st Common Junction to 2nd Common Junction (Peelarmuzhy Anganvadi) - 1500M f) 250mm DI K9 CWGM from 2nd Common Junction to 14LL OHSR-7340m g) 100mm DI K9 CWPM from 2nd Common Junction to 1LL OHSR-370m h) Booster pump house with 5HP Booster pump set at Peelarmuzhy Anganvadi i) Road restoration works
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 586100000
AS Number WRD025-03-PA-01 Dated: 13.11.2018
TS Amount (Rs) 586100000
TS Number TS/2019-2020/2019/17186, 17187 Dated: 22.11.2019
Total Bill Submitted (Rs) 196416508
Total Bill Paid (Rs) 196416508
Population Benefitted 80500
Capacity in MLD 12.00
Actual Project Completion Date Date is not specified
Coverage Kodassery, Pariyaram and Athirappilly panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District-Package 1 Nattika Project Dn
2 KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District- Package-2 Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 May 2024 Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.404/3.7 KM Nattika AE 3
05 May 2024 Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.384/3.7 KM Nattika AE 3
04 May 2024 Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.384/3.7 KM Nattika AE 3
03 May 2024 Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.318/3.7 KM Nattika AE 3
02 May 2024 Package 1-WTP Civil structure work completed. Finishing work & retaining wall work & Internal road formation completed. Mechanical & plumbing work completed. Electrical connection work completed. Intake well- Civil structure work completed. Retaining wall work completed. Mechanical work completed. Electrical connection work completed. Pipe laying RWPM completed. 450 mm DI K9 CWGM-7.502 km/10.23km pipe laid. Package2 - All work completed. Pending laying 2.318/3.7 KM Nattika AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/07/2020
Scheduled date of Completion of the Project 28 Jun 2022
Expected date of Completion 14/09/2024

Processing Dates

AS Date 13 Nov 2018
TS Date 22 Nov 2019