JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat

Project JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat
Project Code TVMJJM08207567
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat
Status On-going
District Thiruvananthapuram
Executing Office Kanjiramkulam WS Sn
AS Amount (Rs) 77200000
AS Number A.S.No.G.O.(RT)No.541/20202/WRD
TS Amount (Rs) 77100000
TS Number TS/2020-2021/19564
Total Bill Submitted (Rs) 35358755
Total Bill Paid (Rs) 38862000
Population Benefitted 8770
Capacity in MLD 2.50
Actual Project Completion Date 25 Jul 2021
Coverage Thirupuram Grama Panchayat various wards
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat Kanjiramkulam WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Jul 2022 work closed final bill submitted Kanjiramkulam AE JJM
04 Jul 2022 work completed CC IX th and final bill prepared Kanjiramkulam AE JJM
30 Jun 2022 work closed Kanjiramkulam AE JJM
27 Jun 2022 work closed Kanjiramkulam AE JJM
22 Jun 2022 work closed Kanjiramkulam AE JJM

Project Review

See All Review messages
Review Date Review Message Review Attended By
23 Feb 2022 Out of 1754 FHTC 1175 nos has been given till date , but around 400 nos beneficiaries not willing to take JJM connection, many attempt made to motivation they are not willing to take connection. As directed by the EE a meeting has to be scheduled on 26.02.2022 at Panchayat Hall

Duration & Sanction dates

Date of start of Project 27/01/2021
Scheduled date of Completion of the Project 26 Jul 2021
Expected date of Completion 28/02/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 20 Sep 2020

Other details

Project Officers View