JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat
Project |
JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat |
Project Code |
TVMJJM08207567 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Kanjiramkulam WS Sn |
AS Amount (Rs) |
77200000
|
AS Number |
A.S.No.G.O.(RT)No.541/20202/WRD |
TS Amount (Rs) |
77100000 |
TS Number |
TS/2020-2021/19564 |
Total Bill Submitted (Rs) |
35358755 |
Total Bill Paid (Rs) |
38862000 |
Population Benefitted |
8770 |
Capacity in MLD |
2.50 |
Actual Project Completion Date |
25 Jul 2021 |
Coverage |
Thirupuram Grama Panchayat various wards |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2020-21 -Thiruvananthapuram District-Thirupuram Grama Panchayat-Phase-II, Providing FHTC's to house holds through retrofitting and pipe line extension in various wards of Thirupuram Grama panchayat |
Kanjiramkulam WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Jul 2022 |
work closed final bill submitted |
Kanjiramkulam AE JJM |
|
04 Jul 2022 |
work completed CC IX th and final bill prepared |
Kanjiramkulam AE JJM |
|
30 Jun 2022 |
work closed |
Kanjiramkulam AE JJM |
|
27 Jun 2022 |
work closed |
Kanjiramkulam AE JJM |
|
22 Jun 2022 |
work closed |
Kanjiramkulam AE JJM |
|
Review Date |
Review Message |
Review Attended By |
23 Feb 2022 |
Out of 1754 FHTC 1175 nos has been given till date , but around 400 nos beneficiaries not willing to take JJM connection, many attempt made to motivation they are not willing to take connection. As directed by the EE a meeting has to be scheduled on 26.02.2022 at Panchayat Hall |
|
Duration & Sanction dates
Date of start of Project |
27/01/2021 |
Scheduled date of Completion of the Project |
26 Jul 2021 |
Expected date of Completion |
28/02/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
20 Sep 2020 |